Select a School...
Select a School

Atherton Elementary School

pic1

Description

Atherton Elementary is located Houston’s fifth ward, where it provides students an academic curriculum to prepare them for middle school. It provides a full range of extracurricular activities, including band and choir.

Scope of Work

New school for up to 750 students.

Project Status

Construction is complete and the project is in warranty. The school staff moved into the new building in July to start the Fall 2013 semester as residents in the new facility. Final documentation is in progress for LEED certification.

Key Facts

  • Budget: $15,914,119
  • Project Type: New Schools: Replacements
  • District: District II - Rhonda Skillern-Jones
  • Location: 2011 Solo

Have a question or comment?

Please submit your question or suggestion about this school project to bondinfo@houstonisd.org
and an HISD representative will follow up.

Information

Indicator
Indicator
ID
C-066 
Project/School/Facility
Budget
$6,752,946 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
4th Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Sizwe Lewis
Architect: Harrison Kornberg Architects
Contractor: DivisionOne Construction
CMPA: N/A
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/ plumbing systems improvements, restrooms upgrade, bus drive creation, renovation of science labs, and new administration area. 
Status
Phase 2 is near completion. Canopy and bus drive is in progress. New boiler(s) and Chiller installation is moving forward. 
Notes
none 
Indicator
Indicator
ID
C-120 
Project/School/Facility
Budget
$2,956,760 
Target Construction Start
4th Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: Ambrose McEnany & House Architects
Contractor: ICI Construction
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, electrical improvements, a suspended ceiling, exterior wall finishes, a new PA system, new door hardware, restroom upgrades, paving improvements, and ADA code compliance. 
Status
Final permit inspections are being performed on the renovation contract. Revised closeout documents are being submitted. The upgrade to the main electrical service is complete. 
Notes
The original general contractor was RHJ-JOC Inc., which defaulted on their contract in December 2012. HISD has since negotiated with the surety company and contracted with a completion contractor to restart and complete the construction scope, as noted in the information section above. 
Indicator
Indicator
ID
C-122 
Project/School/Facility
Budget
$4,898,886 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: Natex Corporation
Contractor: Prime Contractors
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, exterior drainage, reception area modifications, fire alarm upgrade, flooring and fencing replacement, sitework, and ADA code compliance. 
Status
The renovation project is complete and being closed out. 
Notes
A separate roof project is anticipated to be presented for approval to the school board in April 2014, with construction scheduled to occur through the third quarter 2014. 
Indicator
Indicator
ID
C-287 
Project/School/Facility
Budget
$1,140,626 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: RdlR Architects
Contractor: KBR
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
The summer renovation of restrooms, lighting replacement, and accessibility ramp replacement is complete and being closed out. Additional safety/security scope is being reviewed and priced. 
Notes
none 
Indicator
Indicator
ID
C-123 
Project/School/Facility
Budget
$1,755,413 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: PBK Architects
Contractor: Prime Contractors
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, lighting, playground equipment, technology improvements, and ADA code compliance. 
Status
The renovation of this school has been suspended and the students relocated to Rhoads ES. HISD Administration is working with the school leadership to determine next steps. 
Notes
The project schedule has been adjusted to reflect the negotiated schedule with the awarded contractor. 
Indicator
Indicator
ID
C-290 
Project/School/Facility
Budget
$4,454,891 
Target Construction Start
4th Qtr. 2013 
Target Construction Completion
3rd Qtr. 2014 
Phase
Construction 
% of Phase
98% 
Project Team
Manager: Chris Koeper
Architect: Prozign Architects
Contractor: ICI Construction
CMPA: N/A
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Final signage, misc. change orders and air handling unit replacement will take place through second quarter 2014. Controls will be installed concurrently with the air handling unit replacement. Low voltage systems will be installed during the summer of 2014. 
Notes
The original general contractor was RHJ-JOC Inc., which defaulted on their contract in December 2012. HISD has since negotiated with the surety company and contracted with a completion contractor to restart and complete the construction scope, as noted in the information section above. 
Indicator
Indicator
ID
C-044 
Project/School/Facility
Budget
$15,310,098 
Target Construction Start
4th Qtr. 2012 
Target Construction Completion
2nd Qtr. 2014 
Phase
Complete 
% of Phase
100% 
Project Team
Manager: Travis Stanford
Architect: RDC Architects
Contractor: DT Construction Co.
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, parking repairs, science laboratory upgrades, exterior window replacement, and ADA code compliance. 
Status
The renovation project is complete and closed-out. 
Notes
A separate roof project is anticipated to be presented for approval to the school board in April 2014, with construction scheduled to occur through the fourth quarter 2014. 
Indicator
Indicator
ID
C-297 
Project/School/Facility
Budget
$3,606,928 
Target Construction Start
2nd Qtr. 2012 
Target Construction Completion
2nd Qtr. 2014 
Phase
Close-Out 
% of Phase
95% 
Project Team
Manager: Bruce Green
Architect: Molina Walker
Contractor: Prime Contractors
CMPA: Rice & Gardner
 
General Overview
Renovations, including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Closeout Documents have been reviewed and are nearly complete. Roof replacement contract with Rain Seal Master is in progress. 
Notes
none 
Indicator
Indicator
ID
C-045 
Project/School/Facility
Budget
$3,516,752 
Target Construction Start
3rd Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: Collaborate Architects
Contractor: Prime Contractors
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
The change order for the completion of the elevator has been approved. Structural steel is due on site the week of October 6 with installation to follow. Completion is expected by the end of November. 
Notes
none 
Indicator
Indicator
ID
C-139 
Project/School/Facility
Budget
$521,583 
Target Construction Start
TBD 
Target Construction Completion
TBD 
Phase
TBD 
% of Phase
TBD 
Project Team
Manager: Meredith Smith
Architect: PBK Architects
Contractor: TBD
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
This project scope is being re-evaluated. 
Notes
This project was placed on hold to give the Board of Education time to consider repurposing of the campus. 
Indicator
Indicator
ID
C-148 
Project/School/Facility
Budget
$1,248,399 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Close-Out 
% of Phase
90% 
Project Team
Manager: Bruce Green
Architect: Cre8 Architects
Contractor: Prime Contractors
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
This project is in the Shearn, Kolter & Elrod package. The project is substantially complete and now in the close out stage. 
Notes
none 
Indicator
Indicator
ID
C-155 
Project/School/Facility
Budget
$1,432,454 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: Courtney Harper + Partners Architects
Contractor: Jamail + Smith
CMPA: AECOM Design
Annual Vendors: Harrison Alarm
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
The renovation work is substantially complete and the project is being closed out. 
Notes
none 
Indicator
Indicator
ID
C-283 
Project/School/Facility
Budget
$1,521,658 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
1st Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: Natex Corporation
Contractor: Prime Contractors
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical systems upgrades, fire alarm upgrade, intercom replacement, markerboard replacement, flooring and fencing replacement, sitework, and ADA code compliance. 
Status
The renovation project is complete and closed-out. The final pay application will be submitted with the closeout documents for Burbank ES. 
Notes
none 
Indicator
Indicator
ID
C-159 
Project/School/Facility
Budget
$2,214,831 
Target Construction Start
1st Qtr. 2014 
Target Construction Completion
3rd Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: PBK Architects
Contractor: Prime Contractors
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, roofing repairs, technology improvements, and ADA code compliance. 
Status
The creation of a new science classroom and additional conference rooms is substantially complete. The renovation contract is ready for closeout. 
Notes
The project schedule has been adjusted to reflect the negotiated schedule with the awarded contractor. 
Indicator
Indicator
ID
C-262 
Project/School/Facility
Budget
$3,948,795 
Target Construction Start
3rd Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: MLB and Associates
Contractor: Prime Contractors
CMPA: AECOM Design
 
General Overview
Renovations including safety/security improvements, mechanical/electrical/plumbing system improvements, exterior doors, door hardware, restrooms upgrade, replacement of new elevator, and ADA code compliance. 
Status
Closeout documents and the final pay application have been reviewed and are being submitted to HISD. 
Notes
none 
Indicator
Indicator
ID
C-049 
Project/School/Facility
Budget
$2,823,535 
Target Construction Start
4th Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: Ambrose McEnany & House Architects
Contractor: ICI Construction
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, exterior doors, door hardware, restrooms upgrade, replacement of new elevator, and ADA code compliance. 
Status
Final permit inspections are being performed. Revised closeout documents are being submitted. 
Notes
The original general contractor was RHJ-JOC Inc., which defaulted on their contract in December 2012. HISD has since negotiated with the surety company and contracted with a completion contractor to restart and complete the construction scope, as noted in the information section above. 
Indicator
Indicator
ID
C-169 
Project/School/Facility
Budget
$1,703,938 
Target Construction Start
4th Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: Ambrose McEnany & House Architects
Contractor: ICI Construction
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, lighting, exterior, interior doors and hardware, window replacements, restrooms upgrade, fencing and ADA code compliance. 
Status
Final permit inspections are being performed. Revised closeout documents are being submitted. 
Notes
The original general contractor was RHJ-JOC Inc., which defaulted on their contract in December 2012. HISD has since negotiated with the surety company and contracted with a completion contractor to restart and complete the construction scope, as noted in the information section above. 
Indicator
Indicator
ID
C-053 
Project/School/Facility
Budget
$10,616,355 
Target Construction Start
1st Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: English + Associates Architects
Contractor: Comex Corporation
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, new lighting, a new bus canopy, paving repairs, restroom upgrades, improved interior finishes, auditorium seating, bleachers, signage, and ADA code compliance. 
Status
Installation of the new auditorium seating is complete. Renovations in the science building are substantially complete and the renovation of the first floor restrooms will be complete in October. Upgrades to the main electrical service are scheduled for winter break. HVAC system replacement is ongoing. Installation of the new PA system is complete. 
Notes
In addition to the 2007 scope of work the 2012 restroom renovation work will continue with the same project team through third quarter 2015. 
Indicator
Indicator
ID
C-050 
Project/School/Facility
Budget
$3,428,277 
Target Construction Start
4th Qtr. 2012 
Target Construction Completion
4th Qtr. 2013 
Phase
Close-Out 
% of Phase
90% 
Project Team
Manager: Bruce Green
Architect: Ambrose & House
Contractor: Prime Contractors
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements and ADA code compliance. 
Status
Construction is complete and in the closeout phase. The project is under warranty. 
Notes
none 
Indicator
Indicator
ID
C-054 
Project/School/Facility
Budget
$14,347,354 
Target Construction Start
1st Qtr. 2011 
Target Construction Completion
3rd Qtr. 2012 
Phase
Close-Out 
% of Phase
90% 
Project Team
Manager: Bruce Green
Architect: Autoarch Architects
Contractor: Summit Builders
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Closeout documents are complete. The original contractor failed to complete punch list items. A job order contractor and annual vendors are completing this work at the cost of the original contractor. 
Notes
none 
Indicator
Indicator
ID
C-182 
Project/School/Facility
Budget
$1,526,081 
Target Construction Start
1st Qtr. 2012 
Target Construction Completion
1st Qtr. 2014 
Phase
Close-Out 
% of Phase
50% 
Project Team
Manager: Meredith Smith
Architect: Corgan+PBA
Contractor: First Nat. Ins./Comex
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, restroom upgrades, roof repairs, parking lot expansion, and ADA code compliance. 
Status
Punch list work is nearing completion. 
Notes
The original general contractor was RHJ-JOC Inc., which defaulted on their contract in December 2012. HISD has since negotiated with the surety company and contracted with a completion contractor to restart and complete the construction scope, as noted in the information section above. 
Indicator
Indicator
ID
C-055 
Project/School/Facility
Budget
$10,779,749 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: RWS Architects
Contractor: ICI Construction
CMPA: Rice & Gardner Consultants, Inc.
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, refurbishing exterior and interior finishes, science laboratory upgrades, and ADA code compliance modifications. 
Status
Construction is near completion. 
Notes
Phase 1 was completed and project team is in final negotiations for close-out of the original contract. 
Indicator
Indicator
ID
C-079 
Project/School/Facility
Budget
$4,348,962 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
3rd Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: Hill + Swart Architects, Inc.
Contractor: KBR
CMPA: AECOM Design
 
General Overview
Renovations include safety/security systems improvements, mechanical/electrical/plumbing systems, fire alarm repair, intercom replacement, door and hardware replacement, science lab venting and fume hoods, sitework, construction of a fire truck access lane, and ADA code compliance. 
Status
The lighting replacement is complete with final permit inspections proceeding. The project will be closed out in October. 
Notes
none 
Indicator
Indicator
ID
C-189 
Project/School/Facility
Budget
$737,591 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
3rd Qtr. 2014 
Phase
Close-Out 
% of Phase
90% 
Project Team
Manager: Bruce Green
Architect: Cre8 Architects
Contractor: Prime Contractors
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements and ADA code compliance. 
Status
This project is in the Shearn, Kolter & Elrod package. The project is substantially complete and now in the close out stage. 
Notes
none 
Indicator
Indicator
ID
C-263 
Project/School/Facility
Budget
$1,658,041 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
3rd Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: PBK Architects
Contractor: Prime Contractors
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, technology improvements, and ADA code compliance. 
Status
The renovation project is substantially complete, punchlist work is ongoing, and closeout documents are being prepared. 
Notes
The project schedule has been adjusted to reflect the negotiated schedule with the awarded contractor. 
Indicator
Indicator
ID
C-128 
Project/School/Facility
Budget
$1,902,951 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
1st Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: Natex Architects
Contractor: Prime Contractors
CMPA: AECOM Design
 
General Overview
Renovations include safety/security systems improvements, mechanical and electrical systems upgrades, fire alarm upgrade, intercom replacement, marker board replacement, parking lot expansion, flooring replacement, sitework, and ADA code compliance. 
Status
The renovation project is complete and being closed out. The final pay application will be submitted with the close out documents for Burbank ES. 
Notes
none 
Indicator
Indicator
ID
C-201 
Project/School/Facility
Budget
$1,042,813 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: RWS Architects
Contractor: Jamail & Smith, Ohms Electric, CLS, AMS
CMPA: AECOM Design
 
General Overview
Renovations including replacing electrical system components, resolution of structural issues, door repairs, PA system and ADA code compliance, tree trimming and treatment, and masonry repairs. 
Status
The project is substantially complete and closeout documents are being reviewed. 
Notes
none 
Indicator
Indicator
ID
C-062 
Project/School/Facility
Budget
$12,053,989 
Target Construction Start
3rd Qtr. 2012 
Target Construction Completion
3rd Qtr. 2013 
Phase
Close-Out 
% of Phase
90% 
Project Team
Manager: Bruce Green
Architect: Autoarch Architects
Contractor: Satterfield & Pontikes
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing, and ADA code compliance. This project will also include an addition to the school that features a science lab and classrooms. 
Status
Construction is complete and in the closeout phase. The project is under warranty. 
Notes
Additional egress lighting is being installed by annual vendor. 
Indicator
Indicator
ID
C-222 
Project/School/Facility
Budget
$839,304 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
3rd Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: STOA International Architects
Contractor: Jamail + Smith
CMPA: AECOM Design
Annual Vendor: Atlas Signs
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Installation of the new lighting and marker boards will be complete in October. Replacement of the main electrical service weather head has been approved. 
Notes
none 
Indicator
Indicator
ID
C-223 
Project/School/Facility
Budget
$3,434,141 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: RdlR Architects
Contractor: Level Infrastructure, LLC
CMPA: AECOM Design
 
General Overview
Renovations, including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Renovation of the pre-K classrooms, administrative offices and restrooms, and replacement of exterior canopy walkways was complete at the end of the summer. Phase 2 student restroom renovations will be complete in mid-October with the next restroom renovation phase to follow. 
Notes
none 
Indicator
Indicator
ID
C-060 
Project/School/Facility
Budget
$1,758,507 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Construction 
% of Phase
95% 
Project Team
Manager: Bruce Green
Architect: Sustaita Architects
Contractor: DT Construction
CMPA: Rice & Gardner
 
General Overview
Renovations including Replacement of storefronts; floor finishes (VCT, ceramic); ceiling finishes (acoustical tile); science classroom millwork; wall finishes (Paint, ceramic tile); masonry (CMU); restroom partitions, plumbing and fixture upgrades; exhaust fan additions; exterior lighting; site work. 
Status
The new flooring, science classroom, and first floor restroom renovations are complete. The second floor restroom renovations and selected window and door replacements have been completed. 
Notes
In addition to the 2007 scope of work the 2012 restroom renovation work has been added and will be completed with the same project team. 
Indicator
Indicator
ID
C-039 
Project/School/Facility
Budget
$8,177,171 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: Sustaita Architects
Contractor: DT Construction
CMPA: Rice & Gardner Consultants, Inc.
 
General Overview
Renovations including storefront and curtain wall replacement, HVAC replacement and repairs, electrical panel replacement, electrical upgrades, door and window replacement, ceramic tile floor and carpet replacement, restroom renovations, plumbing fixture replacements, drinking fountain additions, millwork upgrades, suspended ceiling repairs and replacement, abatement, PA additions and signage. 
Status
The project is substantially complete and is being closed out. 
Notes
In addition to the 2007 scope of work additional restroom renovations work was added to accommodate the special needs of this school. This additional scope will be completed late second quarter 2014. 
Indicator
Indicator
ID
C-232 
Project/School/Facility
Budget
$3,916,464 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
3rd Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: Harrison Kornberg Architects
Contractor: Jamail + Smith
CMPA: AECOM Design
Annual Vendor: Ohms Electric, Harrison Alarm
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, roof repairs, restrooms upgrade, science laboratory upgrades, elevator installation, and ADA code compliance. 
Status
The renovation work is substantially complete and the project is being closed out. 
Notes
none 
Indicator
Indicator
ID
C-234 
Project/School/Facility
Budget
$11,514,609 
Target Construction Start
1st Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: STOA International Architects
Contractor: Satterfield & Pontikes
CMPA: Rice & Gardner Consultants, Inc
 
General Overview
A middle school addition and renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
The school has moved into the new addition. Final site work, punch list and closeout is ongoing. 
Notes
A separate roof project is anticipated to be presented for approval to the school board in April 2014, with construction scheduled to occur through the third quarter 2014. 
Indicator
Indicator
ID
C-281 
Project/School/Facility
Budget
$854,366 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
3rd Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: Courtney Harper + Partners Architects
Contractor: Jamail + Smith
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements and ADA compliance. 
Status
The renovation work is substantially complete and project is being closed out. 
Notes
none 
Indicator
Indicator
ID
C-239 
Project/School/Facility
Budget
$2,479,845 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
4th Qtr. 2013 
Phase
Close-Out 
% of Phase
90% 
Project Team
Manager: Bruce Green
Architect: Cre8 Architects
Contractor: Prime Contractors
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, site work, exterior and interior finishes, technology systems improvements, and ADA code compliance. 
Status
This project is in the Shearn, Kolter & Elrod package. The project is substantially complete and now in the close out stage. 
Notes
none 
Indicator
Indicator
ID
C-240 
Project/School/Facility
Budget
$18,189,731 
Target Construction Start
3rd Qtr. 2012 
Target Construction Completion
4th Qtr. 2013 
Phase
Close-Out 
% of Phase
90% 
Project Team
Manager: Travis Stanford
Architect: Collaborate
Contractor: Comex Corporation
CMPA: N/A
 
General Overview
New school for 750 students. 
Status
Construction is complete and is in the warranty phase. Certificate of Occupancy has been obtained. The campus occupied the new facility fourth quarter 2013. Final documentation is in progress for LEED certification. 
Notes
none 
Indicator
Indicator
ID
C-242 
Project/School/Facility
Budget
$17,050,846 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Travis Stanford
Architect: Brave Architecture
Contractor: Comex Corporation
CMPA: N/A
 
General Overview
School expansion. 
Status
Construction for the final phase (cafeteria, library and parking lot) is underway. The parking lot is 90% complete and is use by the school staff. Sitework and foundation for the building is approximately 20% and progressing well. Work is on schedule for Fall semester 2015 occupancy. 
Notes
The additional scope of work, including the library and cafeteria will be completed second quarter 2015. 
Indicator
Indicator
ID
C-244 
Project/School/Facility
Budget
$13,493,587 
Target Construction Start
3rd Qtr. 2012 
Target Construction Completion
2nd Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: Collaborate Architects
Contractor: Morganti Construction
CMPA: Rice & Gardner Consultants, Inc.
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. This project will include two additions to the school, a new multi-purpose building and a new Administration/Library wing. An additional project to replace the roof is currently planned for the third quarter 2014. 
Status
The construction is near completion. 
Notes
A separate roof project was approved by the school board in April 2014, with construction scheduled to occur through the third quarter 2014. 
Indicator
Indicator
ID
C-098 
Project/School/Facility
Budget
$3,230,362 
Target Construction Start
2nd Qtr. 2012 
Target Construction Completion
4th Qtr. 2013 
Phase
Close-Out 
% of Phase
90% 
Project Team
Manager: Bruce Green
Architect: RWS Architects
Contractor: Prime Contractors
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Construction is complete and in the closeout phase. The project is under warranty. 
Notes
none 
Indicator
Indicator
ID
C-248 
Project/School/Facility
Budget
$6,310,699 
Target Construction Start
1st Qtr. 2012 
Target Construction Completion
4th Qtr. 2013 
Phase
Close-Out 
% of Phase
90% 
Project Team
Manager: Bruce Green
Architect: Pfluger Associates
Contractor: Solidarity / Jamail & Smith
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, exterior finishes, and ADA code compliance. 
Status
Minor punch list items are remaining to be completed. The HVAC replacement work is complete. Project is substantially complete. 
Notes
none 
Indicator
Indicator
ID
C-252 
Project/School/Facility
Budget
$3,177,976 
Target Construction Start
1st Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: RWS Architects
Contractor: Comex Corporation
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, replacing lighting, flooring, casework, ceilings in classrooms, revising admin area, new PA building alarm and fire alarm system. 
Status
The renovation work is substantially complete, punchlist work is underway, and the project is being closed out. 
Notes
none 
Indicator
Indicator
ID
C-258 
Project/School/Facility
Budget
$3,712,925 
Target Construction Start
4th Qtr. 2013 
Target Construction Completion
3rd Qtr. 2014 
Phase
Construction 
% of Phase
95% 
Project Team
Manager: Chris Koeper
Architect: Prozign Architects
Contractor: ICI Construction
CMPA: N/A
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Renovation and interior finishes are ongoing, including the elevator installation and misc. long lead items. Low voltage systems will be complete by third quarter 2014. 
Notes
The original schedule was to start construction second quarter 2012 with an anticipated completion being first quarter 2013. The general contractor was RHJ-JOC Inc., which defaulted on their contract in December 2012. HISD has since negotiated with the surety company and contracted with a completion contractor to restart and complete the construction scope, as noted in the information section above. 
Indicator
Indicator
ID
C-260 
Project/School/Facility
Budget
$4,252,358 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Closeout 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: VLK Architects
Contractor: Renovation — Patriot Construction; Window Replacement — Jamail & Smith
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, interior and exterior finishes, windows, technology improvements, and ADA code compliance. 
Status
The window replacement, marker board/window blinds replacement package, and student restroom renovation summer work packages are complete and being closed out. 
Notes
none 
Last Updated: 12/13/2013
CLOSE