Description

Atherton Elementary is located Houston’s fifth ward, where it provides students an academic curriculum to prepare them for middle school. It provides a full range of extracurricular activities, including band and choir.

Scope of Work

New school for up to 750 students.

Project Status

Construction is complete and the project is in warranty. The school staff moved into the new building in July to start the Fall 2013 semester as residents in the new facility. Final documentation is in progress for LEED certification.

Key Facts

  • Budget: $15,914,119
  • Project Type: New Schools: Replacements
  • District: District II - Rhonda Skillern-Jones
  • Location: 2011 Solo

Have a question or comment?

Please submit your question or suggestion about this school project to bondinfo@houstonisd.org
and an HISD representative will follow up.

Information

Indicator
Indicator
ID
C-106 
Project/School/Facility
Budget
$15,914,119 
Target Construction Start
3rd Qtr. 2011 
Target Construction Completion
2nd Qtr. 2013 
Phase
Warranty 
% of Phase
50% 
Project Team
Manager: Travis Stanford
Architect: IDG Architects
Contractor: Cadence McShane
CMPA: N/A
 
General Overview
New school for up to 750 students. 
Status
Construction is complete and the project is in warranty. The school staff moved into the new building in July to start the Fall 2013 semester as residents in the new facility. Final documentation is in progress for LEED certification. 
Notes
none 
Indicator
Indicator
ID
C-066 
Project/School/Facility
Budget
$6,791,693 
Target Construction Start
2nd Qtr. 2013 / 2nd Qtr. 2014 
Target Construction Completion
3rd Qtr. 2013 / 3rd Qtr. 2014 
Phase
Warranty / Design 
% of Phase
15% / 50% 
Project Team
Manager: Chris Koeper
Architect: Harrison Kornberg
Contractor: DivisionOne
CMPA: N/A
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, restrooms upgrade, bus drive creation, renovation of science labs, and new administration area. 
Status
The first phase conversion of Ryan MS in to the Baylor College of Medicine @ Ryan was successfully accomplished for the 2013/2014 School year. The second phase scope of work to accommodate the future expansion of the program is being finalized with the A/E, GC, and HISD’s Academics department. CD development for the second phase is scheduled to be complete the 1st qtr. of 2014. 
Notes
none 
Indicator
Indicator
ID
C-120 
Project/School/Facility
Budget
$2,602,542 
Target Construction Start
4th Qtr. 2013 
Target Construction Completion
1st Qtr. 2014 
Phase
Construction 
% of Phase
75% 
Project Team
Manager: Meredith Smith
Architect: Ambrose & House
Contractor: ICI Construction
CMPA: AECOM
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, electrical improvements, a suspended ceiling, exterior wall finishes, a new PA system, new door hardware, restroom upgrades, paving improvements, and ADA code compliance. 
Status
The agreement between the Surety and HISD to complete the renovation work has been executed. The Notice to Proceed has been issued. Renovation of the student restrooms is ongoing. Replacement of AC units in the library and cafeteria is nearing completion. 
Notes
The original schedule was to start construction 2nd Qtr. 2012 with an anticipated completion being 1st Qtr. 2013. The general contractor was RHJ-JOC Inc., which defaulted on their contract in December 2012. HISD has since negotiated with the surety company and contracted with a completion contractor to restart and complete the construction scope, as noted in the information section above. 
Indicator
Indicator
ID
C-122 
Project/School/Facility
Budget
$3,669,729 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Construction 
% of Phase
20% 
Project Team
Manager: Meredith Smith
Architect: Natex Corporation
Contractor: Prime Contractors
CMPA: N/A
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, exterior drainage, reception area modifications, fire alarm upgrade, flooring and fencing replacement, sitework, and ADA code compliance. 
Status
Group 4 Project - Renovation of first 4 classrooms is complete. Site work is ongoing. Contractor is working to improve schedule after delay for permit review of minor revisions. Renovation of 6 small rooms into 3 new classrooms is near completion. 
Notes
none 
Indicator
Indicator
ID
C-287 
Project/School/Facility
Budget
$1,074,475 
Target Construction Start
1st Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Design 
% of Phase
65% 
Project Team
Manager: Bruce Green
Architect: RdlR Architects
Contractor: TBD
CMPA: Johnston, LLC
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Design development documents are being reviewed by HISD’s Design Department. 
Notes
none 
Indicator
Indicator
ID
C-322 
Project/School/Facility
Budget
$22,705,543 
Target Construction Start
2nd Qtr. 2011 / 4th Qtr. 2012 
Target Construction Completion
3rd Qtr. 2012 / 3rd Qtr. 2013 
Phase
Warranty / Warranty 
% of Phase
100% / 25% 
Project Team
Manager: Meredith Smith
Architect: RdlR Architects
Contractor: Turner / Pyramid
CMPA: N/A
 
General Overview
New school to accommodate 600 students on property adjacent to Gregory-Lincoln Education Center. A parking deck and field improvements were added to the scope through an interlocal agreement with the City of Houston. Build-out of the existing Settegast Building for fine arts classrooms and a theater was added through Trustee allocations. 
Status
The new school opened for the 2012-2013 academic year. The Settegast fine arts building opened for the 2013-2014 academic year. 
Notes
none 
Indicator
Indicator
ID
C-123 
Project/School/Facility
Budget
$1,650,032 
Target Construction Start
1st Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Design 
% of Phase
100% 
Project Team
Manager: Travis Stanford
Architect: PBK Architects
Contractor: TBD
CMPA: Atser
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, lighting, playground equipment, technology improvements, and ADA code compliance. 
Status
Group 4 Project, PBK Architects have completed the design of the project and the plans are in the City of Houston for permitting. Golfcrest ES, Law ES, Dodson ES and Codwell ES will be combined in 1 bid package for construction. 
Notes
The percentage complete of the design phase reflects the status of design, which now includes the additional construction scope. 
Indicator
Indicator
ID
C-290 
Project/School/Facility
Budget
$4,295,779 
Target Construction Start
4th Qtr. 2013 
Target Construction Completion
3rd Qtr. 2014 
Phase
Construction 
% of Phase
70% 
Project Team
Manager: Chris Koeper
Architect: Prozign Architects
Contractor: ICI Construction
CMPA: Johnston, LLC
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
The agreement between the Surety and HISD to complete the renovation work has been executed. The Notice to Proceed has been issued and we are working towards obtaining our permit transfer with the City of Houston. Renovation work is expected to start the 1st quarter of 2014. 
Notes
The original schedule was to start construction 2nd Qtr. 2012 with an anticipated completion being 1st Qtr. 2013. The general contractor was RHJ-JOC Inc., which defaulted on their contract in December 2012. HISD has since negotiated with the surety company and contracted with a completion contractor to restart and complete the construction scope, as noted in the information section above. 
Indicator
Indicator
ID
C-044 
Project/School/Facility
Budget
$14,542,604 
Target Construction Start
4th Qtr. 2012 
Target Construction Completion
1st Qtr. 2014 
Phase
Construction 
% of Phase
97% 
Project Team
Manager: Travis Stanford
Architect: RDC Architects
Contractor: DT Construction Co.
CMPA: ATSER
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, parking repairs, science laboratory upgrades, exterior window replacement, and ADA code compliance. 
Status
The GC is proceeding with renovations in auditorium, band hall. Window replacement scope, replacement of HVAC systems in vocational rooms and the cafeteria are in progress. The structural slab repairs in Band Hall are in progress. 
Notes
none 
Indicator
Indicator
ID
C-297 
Project/School/Facility
Budget
$3,870,390 
Target Construction Start
2nd Qtr. 2012 
Target Construction Completion
4th Qtr. 2013 
Phase
Warranty 
% of Phase
90% 
Project Team
Manager: Bruce Green
Architect: Molina Walker
Contractor: Prime Contractors
CMPA: Johnston, LLC
 
General Overview
Renovations, including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Original contract work is complete. Closeout Documents have been reviewed and are Complete. Roof replacement contract with Rain Seal Master is in progress. 
Notes
none 
Indicator
Indicator
ID
C-045 
Project/School/Facility
Budget
$3,416,394 
Target Construction Start
3rd Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Construction 
% of Phase
15% 
Project Team
Manager: Bruce Green
Architect: Collaborate Architects
Contractor: Prime Contractors
CMPA: Johnston, LLC
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Notice to Proceed was issued to the contractor on September 4, 2013. Phase One is nearing completion. 
Notes
none 
Indicator
Indicator
ID
C-139 
Project/School/Facility
Budget
$521,583 
Target Construction Start
1st Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Design 
% of Phase
100% 
Project Team
Manager: Travis Stanford
Architect: PBK Architects
Contractor: TBD
CMPA: ATSER
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Group 4 Project. PBK Architects have completed the design of the project and the plans are in the City of Houston for permitting. Golfcrest ES, Law ES, Dodson ES and Codwell ES will be combined into 1 bid package for construction. 
Notes
none 
Indicator
Indicator
ID
C-238 
Project/School/Facility
Budget
$19,626,497 
Target Construction Start
2nd Qtr. 2012 
Target Construction Completion
2nd Qtr. 2013 
Phase
Warranty 
% of Phase
25% 
Project Team
Manager: Bruce Green
Architect: ESPA Architecture
Contractor: Cadence McShane
CMPA: N/A
 
General Overview
New school for 750 students. 
Status
School started successfully in the new facility for 2013-2014 school year. The project is in the closeout phase. 
Notes
none 
Indicator
Indicator
ID
C-115 
Project/School/Facility
Budget
$820,006 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
4th Qtr. 2013 
Phase
Construction 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: RWS Architects
Contractor: Jamail & Smith, Convergint, Ohms Electric
CMPA: AECOM
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, a new PA system, window replacements, and ADA code compliance. 
Status
The following work is complete: courtyard regrading and planting, overlays of walkways for ADA compliance, PA system renovation, intrusion alarm system and rewiring of computer classroom. 
Notes
none 
Indicator
Indicator
ID
C-148 
Project/School/Facility
Budget
$1,248,399 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
4th Qtr. 2013 
Phase
Construction 
% of Phase
95% 
Project Team
Manager: Bruce Green
Architect: Cre8 Architects
Contractor: Prime Contractors
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Partial restroom and door replacement work is complete and the MEP and safety/security upgrades are ongoing. The electrical switchover is scheduled for the winter break. This projects is in the Shearn, Kolter & Elrod package. 
Notes
none 
Indicator
Indicator
ID
C-155 
Project/School/Facility
Budget
$1,376,369 
Target Construction Start
1st Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Design 
% of Phase
85% 
Project Team
Manager: Bruce Green
Architect: Courtney Harper
Contractor: TBD
CMPA: Johnston, LLC
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
95% Construction Documents are being reviewed by HISD’s Design Department. 
Notes
none 
Indicator
Indicator
ID
C-283 
Project/School/Facility
Budget
$1,489,948 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
1st Qtr. 2014 
Phase
Construction 
% of Phase
80% 
Project Team
Manager: Meredith Smith
Architect: Natex Corporation
Contractor: Prime Contractors
CMPA: N/A
 
General Overview
Renovations including safety/security systems improvements, mechanical systems upgrades, fire alarm upgrade, intercom replacement, markerboard replacement, flooring and fencing replacement, sitework, and ADA code compliance. 
Status
Group 4 Project - Flooring replacement is complete and a new boiler is operational. 
Notes
none 
Indicator
Indicator
ID
C-159 
Project/School/Facility
Budget
$1,250,726 
Target Construction Start
3rd Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Design 
% of Phase
100% 
Project Team
Manager: Travis Stanford
Architect: PBK Architects
Contractor: TBD
CMPA: ATSER
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, roofing repairs, technology improvements, and ADA code compliance. 
Status
Group 4 project. PBK Architects have completed the design of the project and the plans are in the City of Houston for permitting. Golfcrest ES, Law ES, Dodson ES and Codwell ES will be combined in 1 bid package for construction. 
Notes
none 
Indicator
Indicator
ID
C-262 
Project/School/Facility
Budget
$3,892,925 
Target Construction Start
3rd Qtr. 2013 
Target Construction Completion
1st Qtr. 2014 
Phase
Construction 
% of Phase
15% 
Project Team
Manager: Travis Stanford
Architect: MLB and Associates
Contractor: Prime Contractors
CMPA: ATSER
 
General Overview
Renovations including safety/security improvements, mechanical/electrical/plumbing system improvements, exterior doors, door hardware, restrooms upgrade, replacement of new elevator, and ADA code compliance. 
Status
Phase I renovation is in process. The GC is performing renovations in classrooms and restrooms. Phase 2 renovations are scheduled to begin the 1st quarter of 2014. All known abatement and testing have been completed. 
Notes
none 
Indicator
Indicator
ID
C-049 
Project/School/Facility
Budget
$2,142,370 
Target Construction Start
4th Qtr. 2013 
Target Construction Completion
1st Qtr. 2014 
Phase
Construction 
% of Phase
75% 
Project Team
Manager: Meredith Smith
Architect: Ambrose & House
Contractor: ICI Construction
CMPA: AECOM
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, exterior doors, door hardware, restrooms upgrade, replacement of new elevator, and ADA code compliance. 
Status
The agreement between the surety and HISD to complete the renovation work has been executed. The Notice to Proceed has been issued. Renovation of the science labs continues. Electrical upgrades and door hardware replacement is progressing. 
Notes
The original schedule was to start construction 2nd Qtr. 2012 with an anticipated completion being 1st Qtr. 2013. The general contractor was RHJ-JOC Inc., which defaulted on their contract in December 2012. HISD has since negotiated with the surety company and contracted with a completion contractor to restart and complete the construction scope, as noted in the information section above. 
Indicator
Indicator
ID
C-169 
Project/School/Facility
Budget
$1,989,761 
Target Construction Start
4th Qtr. 2013 
Target Construction Completion
1st Qtr. 2014 
Phase
Construction 
% of Phase
75% 
Project Team
Manager: Meredith Smith
Architect: Ambrose & House
Contractor: ICI Construction
CMPA: AECOM
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, lighting, exterior, interior doors and hardware, window replacements, restrooms upgrade, fencing and ADA code compliance. 
Status
The agreement between the surety and HISD to complete the renovation work has been executed. The Notice to Proceed has been approved. Replacement of unit ventilators and exhaust fans is progressing. 
Notes
The original schedule was to start construction 2nd Qtr. 2012 with an anticipated completion being 1st Qtr. 2013. The general contractor was RHJ-JOC Inc., which defaulted on their contract in December 2012. HISD has since negotiated with the surety company and contracted with a completion contractor to restart and complete the construction scope, as noted in the information section above. 
Indicator
Indicator
ID
C-171 
Project/School/Facility
Budget
$1,782,476 
Target Construction Start
2nd Qtr. 2012 
Target Construction Completion
3rd Qtr. 2012 
Phase
Warranty 
% of Phase
70% 
Project Team
Manager: Bruce Green
Architect: Sustaita Architects
Contractor: Drymalla Const.
CMPA: Johnston, LLC
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Project is complete. Warranty period is in progress. 
Notes
none 
Indicator
Indicator
ID
C-053 
Project/School/Facility
Budget
$9,065,671 
Target Construction Start
1st Qtr. 2014 
Target Construction Completion
3rd Qtr. 2015 
Phase
Design 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: English + Associates
Contractor: TBD
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, new lighting, a new bus canopy, paving repairs, restroom upgrades, improved interior finishes, auditorium seating, bleachers, signage, and ADA code compliance. 
Status
Competitive Sealed Proposals have been received and are currently being evaluated. 
Notes
none 
Indicator
Indicator
ID
C-050 
Project/School/Facility
Budget
$3,844,773 
Target Construction Start
4th Qtr. 2012 
Target Construction Completion
4th Qtr. 2013 
Phase
Construction 
% of Phase
99% 
Project Team
Manager: Bruce Green
Architect: Ambrose & House
Contractor: Prime Contractors
CMPA: Johnston, LLC
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements and ADA code compliance. 
Status
Construction is complete and in the closeout phase. The project is under warranty. Final Test and Balance is nearing completion. 
Notes
none 
Indicator
Indicator
ID
C-054 
Project/School/Facility
Budget
$14,369,597 
Target Construction Start
1st Qtr. 2011 
Target Construction Completion
3rd Qtr. 2012 
Phase
Warranty 
% of Phase
90% 
Project Team
Manager: Bruce Green
Architect: AUTOARCH
Contractor: Summit Builders
CMPA: Johnston, LLC
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Closeout documents are complete. Fire alarm repairs and miscellaneous scope item are currently being completed by JOC contractors and annual vendors. 
Notes
none 
Indicator
Indicator
ID
C-182 
Project/School/Facility
Budget
$1,526,081 
Target Construction Start
1st Qtr. 2012 
Target Construction Completion
1st Qtr. 2014 
Phase
Construction 
% of Phase
96% 
Project Team
Manager: Meredith Smith
Architect: Corgan+PBA
Contractor: RHJ/First Nat. Ins.
CMPA: N/A
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, restroom upgrades, roof repairs, parking lot expansion, and ADA code compliance. 
Status
Construction is near completion with punchlist work to be completed under agreement with bonding surety. Parking lot expansion to replace street parking has been completed. 
Notes
none 
Indicator
Indicator
ID
C-055 
Project/School/Facility
Budget
$9,879,658 
Target Construction Start
1st Qtr. 2011 
Target Construction Completion
3rd Qtr. 2012 
Phase
Warranty 
% of Phase
100% 
Project Team
Manager: Bruce Green
Architect: RWS Architects
Contractor: Fort Bend Mech.
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, refurbishing exterior and interior finishes, science laboratory upgrades, and ADA code compliance modifications. 
Status
Project is in the final negotiations of settlement. 
Notes
none 
Indicator
Indicator
ID
C-079 
Project/School/Facility
Budget
$4,304,767 
Target Construction Start
1 Qtr. 2014 
Target Construction Completion
3rd Qtr. 2014 
Phase
Design 
% of Phase
95% 
Project Team
Manager: Meredith Smith
Architect: Hill + Swart
Contractor: TBD
CMPA: N/A
 
General Overview
Renovations include safety/security systems improvements, mechanical/electrical/plumbing systems, fire alarm repair, intercom replacement, door and hardware replacement, science lab venting and fume hoods, sitework, construction of a fire truck access lane, and ADA code compliance. 
Status
Final cost review is in progress. This work will augment various building envelope and air conditioning system upgrades performed on this campus during the very early stages of the 2007 Program. 
Notes
none 
Indicator
Indicator
ID
C-189 
Project/School/Facility
Budget
$737,591 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
4th Qtr. 2013 
Phase
Construction 
% of Phase
98% 
Project Team
Manager: Bruce Green
Architect: Cre8 Architects
Contractor: Prime Contractors
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements and ADA code compliance. 
Status
The HVAC replacement in the administration area and the partial window replacements are complete. This projects is in the Shearn, Kolter & Elrod package. 
Notes
none 
Indicator
Indicator
ID
C-263 
Project/School/Facility
Budget
$1,365,658 
Target Construction Start
1st Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Design 
% of Phase
100% 
Project Team
Manager: Travis Stanford
Architect: PBK Architects
Contractor: TBD
CMPA: ATSER
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, technology improvements, and ADA code compliance. 
Status
Group 4 project. PBK Architects have completed the design of the project and the plans are in the City of Houston for permitting. Golfcrest ES, Law ES, Dodson ES and Codwell ES will be combined in 1 bid package for construction. 
Notes
none 
Indicator
Indicator
ID
C-128 
Project/School/Facility
Budget
$1,872,274 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
1st Qtr. 2014 
Phase
Construction 
% of Phase
80% 
Project Team
Manager: Meredith Smith
Architect: Natex Architects
Contractor: Prime Contractors
CMPA: N/A
 
General Overview
Renovations include safety/security systems improvements, mechanical and electrical systems upgrades, fire alarm upgrade, intercom replacement, marker board replacement, parking lot expansion, flooring replacement, sitework, and ADA code compliance. 
Status
Group 4 Project - Flooring replacement is complete and a new boiler is operational. 
Notes
none 
Indicator
Indicator
ID
C-201 
Project/School/Facility
Budget
$1,380,693 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
1st Qtr. 2014 
Phase
Construction 
% of Phase
75% 
Project Team
Manager: Meredith Smith
Architect: RWS Architects
Contractor: Jamail & Smith, Ohms Electric, CLS, AMS
CMPA: AECOM
 
General Overview
Renovations including replacing electrical system components, resolution of structural issues, door repairs, PA system and ADA code compliance. 
Status
Renovation work is nearly complete. Tree trimming and treatment along with masonry repairs are being scheduled. 
Notes
none 
Indicator
Indicator
ID
C-062 
Project/School/Facility
Budget
$11,500,489 
Target Construction Start
3rd Qtr. 2012 
Target Construction Completion
3rd Qtr. 2013 
Phase
Warranty 
% of Phase
15% 
Project Team
Manager: Bruce Green
Architect: AUTOARCH
Contractor: Satterfield & Pontikes
CMPA: Johnston, LLC
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing, and ADA code compliance. This project will also include an addition to the school that features a science lab and classrooms. 
Status
Construction is complete and in the closeout phase. The project is under warranty. Additional scope items, being performed by others, are nearing completion. 
Notes
none 
Indicator
Indicator
ID
C-222 
Project/School/Facility
Budget
$1,025,084 
Target Construction Start
TBD 
Target Construction Completion
TBD 
Phase
Design 
% of Phase
100% 
Project Team
Manager: Bruce Green
Architect: STOA International
Contractor: TBD
CMPA: Johnston, LLC
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
The project’s scope is being evaluated to verify that the scope of work meets the current needs of the facility while maintaining the project’s budget. Safety and security needs are being addressed in the interim. 
Notes
none 
Indicator
Indicator
ID
C-223 
Project/School/Facility
Budget
$3,000,326 
Target Construction Start
1st Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Design 
% of Phase
65% 
Project Team
Manager: Bruce Green
Architect: RdlR Architects
Contractor: TBD
CMPA: Johnston, LLC
 
General Overview
Renovations, including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
The Design Development documents are under review by the CMPA and HISD. 
Notes
none 
Indicator
Indicator
ID
C-060 
Project/School/Facility
Budget
$1,758,335 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
4th Qtr. 2013 
Phase
Construction 
% of Phase
95% 
Project Team
Manager: Bruce Green
Architect: Sustaita Architects
Contractor: DT Construction
CMPA: Rice & Gardner
 
General Overview
Renovations including Replacement of storefronts; floor finishes (VCT, ceramic); ceiling finishes (acoustical tile); science classroom millwork; wall finishes (Paint, ceramic tile); masonry (CMU); restroom partitions, plumbing and fixture upgrades; exhaust fan additions; exterior lighting; site work. 
Status
New flooring and science classroom renovations are complete, along with the first floor restrooms. The second floor restroom renovations and select window and door replacements have been completed. 
Notes
none 
Indicator
Indicator
ID
C-039 
Project/School/Facility
Budget
$7,652,171 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
1st Qtr. 2014 
Phase
Construction 
% of Phase
75% 
Project Team
Manager: Bruce Green
Architect: Sustaita Architects
Contractor: DT Construction
CMPA: Rice & Gardner
 
General Overview
Renovations including storefront and curtain wall replacement, HVAC replacement and repairs, electrical panel replacement, electrical upgrades, door and window replacement, ceramic tile floor and carpet replacement, restroom renovations, plumbing fixture replacements, drinking fountain additions, millwork upgrades, suspended ceiling repairs and replacement, abatement, PA additions and signage. 
Status
Cafeteria, gymnasium and library renovations are complete, along with the first floor restrooms. The restroom renovations, HVAC upgrades, and select window and door replacements are ongoing. 
Notes
none 
Indicator
Indicator
ID
C-232 
Project/School/Facility
Budget
$3,835,444 
Target Construction Start
1st Qtr. 2014 
Target Construction Completion
3rd Qtr. 2014 
Phase
Design 
% of Phase
75% 
Project Team
Manager: Meredith Smith
Architect: Harrison Kornberg
Contractor: TBD
CMPA: N/A
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, roof repairs, restrooms upgrade, science laboratory upgrades, elevator installation, and ADA code compliance. 
Status
Renovations of the office area and site upgrades are completed. Final scope review and budget reconciliation are in progress. 
Notes
none 
Indicator
Indicator
ID
C-234 
Project/School/Facility
Budget
$11,045,217 
Target Construction Start
1st Qtr. 2013 
Target Construction Completion
4th Qtr. 2013 (New Building) 
Phase
Construction 
% of Phase
85% 
Project Team
Manager: Bruce Green
Architect: STOA International
Contractor: Satterfield & Pontikes
CMPA: Johnston, LLC
 
General Overview
A middle school addition and renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Phase I is complete, Phase II is scheduled for move-in after the new year. 
Notes
Heavy rains have moved the completion of the addition to 1st Qtr. 2014. 
Indicator
Indicator
ID
C-281 
Project/School/Facility
Budget
$802,211 
Target Construction Start
1st Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Design 
% of Phase
85% 
Project Team
Manager: Bruce Green
Architect: Courtney Harper
Contractor: TBD
CMPA: Johnston, LLC
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements and ADA compliance. 
Status
95% Construction Documents are being reviewed by HISD’s Design Department. 
Notes
none 
Indicator
Indicator
ID
C-237 
Project/School/Facility
Budget
$5,297,824 
Target Construction Start
1st Qtr. 2011 
Target Construction Completion
3rd Qtr. 2013 
Phase
Warranty 
% of Phase
100% 
Project Team
Manager: Meredith Smith
Architect: PGAL Architects
Contractor: Prime Contractors
CMPA: Turner/Trevino
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, window replacements, classroom casework replacement, the addition of an elevator and ADA code compliance. 
Status
Project has been completed and closed out. 
Notes
none 
Indicator
Indicator
ID
C-239 
Project/School/Facility
Budget
$2,404,541 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
4th Qtr. 2013 
Phase
Construction 
% of Phase
95% 
Project Team
Manager: Bruce Green
Architect: Cre8 Architects
Contractor: Prime Contractors
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, site work, exterior and interior finishes, technology systems improvements, and ADA code compliance. 
Status
New window installation, administration area and science lab renovations have been completed. The contractor is continuing to work on electrical and mechanical upgrades. This projects is in the Shearn, Kolter & Elrod package. 
Notes
none 
Indicator
Indicator
ID
C-240 
Project/School/Facility
Budget
$18,189,731 
Target Construction Start
3rd Qtr. 2012 
Target Construction Completion
4th Qtr. 2013 
Phase
Warranty 
% of Phase
15% 
Project Team
Manager: Travis Stanford
Architect: Collaborate
Contractor: Comex Corporation
CMPA: N/A
 
General Overview
New school for 750 students. 
Status
The Temporary Certificate of Occupancy (TCO) has been obtained. The punch list is being completed by the contractor. The students have occupied the new facility. 
Notes
none 
Indicator
Indicator
ID
C-242 
Project/School/Facility
Budget
$17,049,186 
Target Construction Start
4th Qtr. 2012 / 4th Qtr. 2013 
Target Construction Completion
4th Qtr. 2013 / 3rd Qtr. 2014 
Phase
Construction / Construction 
% of Phase
100% / 5% 
Project Team
Manager: Travis Stanford
Architect: Brave Architecture
Contractor: Comex Corporation
CMPA: N/A
 
General Overview
School expansion. 
Status
The new classroom/administrative wing (Phase 1) is complete. The school moved into this portion of the building over Thanksgiving weekend, classes started December 2, 2013. The Library and cafeteria (Phase 2) has been approved by the City of Houston and the construction is scheduled to start first quarter of 2014. 
Notes
none 
Indicator
Indicator
ID
C-244 
Project/School/Facility
Budget
$12,725,004 
Target Construction Start
3rd Qtr. 2012 
Target Construction Completion
1st Qtr. 2014 
Phase
Construction 
% of Phase
80% 
Project Team
Manager: Bruce Green
Architect: Collaborate Architects
Contractor: Morganti Const.
CMPA: Johnston, LLC
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. This project will include an addition to the school that features a library, multi-purpose room and administrative office. 
Status
Two classroom wings, cafeteria/kitchen, all restrooms and most of HVAC including new pad mounted transformer and new electrical service was completed for start of school. The construction of the new Library/Admin wing and Multi-Purpose Bldg. will be complete 1st Qtr 2014. 
Notes
none 
Indicator
Indicator
ID
C-098 
Project/School/Facility
Budget
$3,649,258 
Target Construction Start
2nd Qtr. 2012 
Target Construction Completion
4th Qtr. 2013 
Phase
Warranty 
% of Phase
15% 
Project Team
Manager: Bruce Green
Architect: RWS Architects
Contractor: Prime Contractors
CMPA: Johnston, LLC
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
The new controls and control valve installations are complete. The testing and balancing of the HVAC system systems is in progress and new dampers will be installed in some classrooms. Roof repairs are complete. Project Closeout is ongoing. 
Notes
none 
Indicator
Indicator
ID
C-163 
Project/School/Facility
Budget
$4,700,455 
Target Construction Start
3rd Qtr. 2012 
Target Construction Completion
1st Qtr. 2013 
Phase
Warranty 
% of Phase
99% 
Project Team
Manager: Meredith Smith
Architect: Courtney Harper
Contractor: Horizon Group Intl.
CMPA: N/A
 
General Overview
Renovations to convert the former elementary school into a middle school, as well as renovations to the science classrooms and construction of a new gymnasium. 
Status
The new gym opened in January 2013. Field improvements under a separate contract are complete. 
Notes
none 
Indicator
Indicator
ID
C-248 
Project/School/Facility
Budget
$6,310,699 
Target Construction Start
1st Qtr. 2012 / 2nd Qtr. 2013 
Target Construction Completion
4th Qtr. 2013 / 4th Qtr. 2013 
Phase
Construction / Construction 
% of Phase
98% / 95% 
Project Team
Manager: Bruce Green
Architect: Pfluger Associates
Contractor: Solidarity / Jamail & Smith
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, exterior finishes, and ADA code compliance. 
Status
Minor punch list items are remaining to be completed. The HVAC replacement work is nearly complete with final connections underway. 
Notes
none 
Indicator
Indicator
ID
C-252 
Project/School/Facility
Budget
$3,177,976 
Target Construction Start
1st Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Bid 
% of Phase
50% 
Project Team
Manager: Meredith Smith
Architect: RWS Architects
Contractor: Comex Corporation
CMPA: AECOM
 
General Overview
Renovations including safety/security systems improvements, replacing lighting, flooring, casework, ceilings in classrooms, revising admin area, new PA building alarm and fire alarm system. 
Status
Work is complete on the restroom renovations. Remaining renovations are scheduled to begin in early 2014. 
Notes
none 
Indicator
Indicator
ID
C-258 
Project/School/Facility
Budget
$3,134,891 
Target Construction Start
4th Qtr. 2013 
Target Construction Completion
3rd Qtr. 2014 
Phase
Construction 
% of Phase
70% 
Project Team
Manager: Chris Koeper
Architect: Prozign Architects
Contractor: ICI Construction
CMPA: Johnston, LLC
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
The agreement between the Surety and HISD to complete the renovation work has been executed. The Notice to Proceed has been issued and renovation work has started and will continue in to next year. 
Notes
The original schedule was to start construction 2nd Qtr. 2012 with an anticipated completion being 1st Qtr. 2013. The general contractor was RHJ-JOC Inc., which defaulted on their contract in December 2012. HISD has since negotiated with the surety company and contracted with a completion contractor to restart and complete the construction scope, as noted in the information section above. 
Indicator
Indicator
ID
C-260 
Project/School/Facility
Budget
$2,729,711 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Design 
% of Phase
75% 
Project Team
Manager: Meredith Smith
Architect: VLK Architects
Contractor: TBD
CMPA: AECOM
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, interior and exterior finishes, windows, technology improvements, and ADA code compliance. 
Status
Group 4 project. VLK Architects designs for the project are in progress. The Architect is process of assessing additional scope and associated cost for renovations to mechanical system review. The interior renovations will include bathroom upgrades,new sinks and drinking fountain, new windows, fencing and walkways, new bus canopy and bus drop-off area,new signage, alarms,wider doorways, new carpet,blinds,and painting. That work is estimated to take about 16 weeks and will start in mid-June 2014. 
Notes
none 

Last Updated: 12/13/2013