Description

Atherton Elementary is located Houston’s fifth ward, where it provides students an academic curriculum to prepare them for middle school. It provides a full range of extracurricular activities, including band and choir.

Scope of Work

New school for up to 750 students.

Project Status

Construction is complete and the project is in warranty. The school staff moved into the new building in July to start the Fall 2013 semester as residents in the new facility. Final documentation is in progress for LEED certification.

Key Facts

  • Budget: $15,914,119
  • Project Type: New Schools: Replacements
  • District: District II - Rhonda Skillern-Jones
  • Location: 2011 Solo

Have a question or comment?

Please submit your question or suggestion about this school project to bondinfo@houstonisd.org
and an HISD representative will follow up.

Information

Indicator
Indicator
ID
C-066 
Project/School/Facility
Budget
$6,759,807 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
4th Qtr. 2014 
Phase
Construction 
% of Phase
10% 
Project Team
Manager: Chris Koeper
Architect: Harrison Kornberg
Contractor: DivisionOne
CMPA: N/A
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, restrooms upgrade, bus drive creation, renovation of science labs, and new administration area. 
Status
Phase 2 and phase 3 have started. The project team is coordinating with Centerpoint to relocate a gas line that is located under the new bus loop. The design team is finalizing modifications to the construction drawings in order to obtain the interior construction permit from City of Houston. 
Notes
none 
Indicator
Indicator
ID
C-120 
Project/School/Facility
Budget
$2,956,760 
Target Construction Start
4th Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Closeout 
% of Phase
40% 
Project Team
Manager: Meredith Smith
Architect: Ambrose McEnany & House Architects
Contractor: ICI Construction
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, electrical improvements, a suspended ceiling, exterior wall finishes, a new PA system, new door hardware, restroom upgrades, paving improvements, and ADA code compliance. 
Status
The project is substantially complete and closeout documents are being reviewed. Punch list work is ongoing. Completion of the main electrical service upgrades is scheduled for July 
Notes
The original general contractor was RHJ-JOC Inc., which defaulted on their contract in December 2012. HISD has since negotiated with the surety company and contracted with a completion contractor to restart and complete the construction scope, as noted in the information section above. 
Indicator
Indicator
ID
C-122 
Project/School/Facility
Budget
$4,538,996 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Closeout 
% of Phase
65% 
Project Team
Manager: Meredith Smith
Architect: Natex Corporation
Contractor: Prime Contractors
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, exterior drainage, reception area modifications, fire alarm upgrade, flooring and fencing replacement, sitework, and ADA code compliance. 
Status
Closeout documents are being reviewed. 
Notes
A separate roof project is anticipated to be presented for approval to the school board in April 2014, with construction scheduled to occur through the third quarter 2014. 
Indicator
Indicator
ID
C-287 
Project/School/Facility
Budget
$1,107,091 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Construction 
% of Phase
30% 
Project Team
Manager: Bruce Green
Architect: RdlR Architects
Contractor: Job Order Contractor
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Demolition in the restrooms is complete. Drywall and masonry walls are underway. Exterior light fixtures have been ordered. Front walk demolition for replacement is starting. 
Notes
none 
Indicator
Indicator
ID
C-123 
Project/School/Facility
Budget
$1,698,505 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Construction 
% of Phase
25% 
Project Team
Manager: Meredith Smith
Architect: PBK Architects
Contractor: Prime Contractors
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, lighting, playground equipment, technology improvements, and ADA code compliance. 
Status
Slab replacement in the west classroom wings is ongoing. Demolition and drywall framing in the southeast wing is complete. Perimeter fence replacement work is ready to start. Unforeseen conditions in the classroom corridors are requiring replacement of ceilings and wall finishes. 
Notes
The project schedule has been adjusted to reflect the negotiated schedule with the awarded contractor. 
Indicator
Indicator
ID
C-290 
Project/School/Facility
Budget
$4,454,891 
Target Construction Start
4th Qtr. 2013 
Target Construction Completion
3rd Qtr. 2014 
Phase
Construction 
% of Phase
98% 
Project Team
Manager: Chris Koeper
Architect: Prozign Architects
Contractor: ICI Construction
CMPA: N/A
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Final signage, misc. change orders and air handling unit replacement will take place through second quarter 2014. Controls will be installed concurrently with the air handling unit replacement. Low voltage systems will be installed during the summer of 2014. 
Notes
The original general contractor was RHJ-JOC Inc., which defaulted on their contract in December 2012. HISD has since negotiated with the surety company and contracted with a completion contractor to restart and complete the construction scope, as noted in the information section above. 
Indicator
Indicator
ID
C-044 
Project/School/Facility
Budget
$15,304,205 
Target Construction Start
4th Qtr. 2012 
Target Construction Completion
2nd Qtr. 2014 
Phase
Closeout 
% of Phase
65% 
Project Team
Manager: Lloyd Hart
Architect: RDC Architects
Contractor: DT Construction Co.
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, parking repairs, science laboratory upgrades, exterior window replacement, and ADA code compliance. 
Status
The contract with the second recommended proposer was awarded. Execution of contract is anticipated in August. 
Notes
A separate roof project is anticipated to be presented for approval to the school board in April 2014, with construction scheduled to occur through the fourth quarter 2014. 
Indicator
Indicator
ID
C-297 
Project/School/Facility
Budget
$3,606,928 
Target Construction Start
2nd Qtr. 2012 
Target Construction Completion
2nd Qtr. 2014 
Phase
Close-Out 
% of Phase
95% 
Project Team
Manager: Bruce Green
Architect: Molina Walker
Contractor: Prime Contractors
CMPA: Rice & Gardner
 
General Overview
Renovations, including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Closeout Documents have been reviewed and are nearly complete. Roof replacement contract with Rain Seal Master is in progress. 
Notes
none 
Indicator
Indicator
ID
C-045 
Project/School/Facility
Budget
$3,503,169 
Target Construction Start
3rd Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Construction 
% of Phase
90% 
Project Team
Manager: Bruce Green
Architect: Collaborate Architects
Contractor: Prime Contractors
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Unforeseen building conditions has delayed the completion of the elevator. Corrective actions to remedy these issues are being issued by the architect. Substantial completion is expected in the late summer. 
Notes
none 
Indicator
Indicator
ID
C-139 
Project/School/Facility
Budget
$521,583 
Target Construction Start
TBD 
Target Construction Completion
TBD 
Phase
TBD 
% of Phase
TBD 
Project Team
Manager: Meredith Smith
Architect: PBK Architects
Contractor: TBD
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
This project scope is being re-evaluated. 
Notes
This project was placed on hold to give the Board of Education time to consider repurposing of the campus. 
Indicator
Indicator
ID
C-148 
Project/School/Facility
Budget
$1,248,399 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Close-Out 
% of Phase
90% 
Project Team
Manager: Bruce Green
Architect: Cre8 Architects
Contractor: Prime Contractors
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
This project is in the Shearn, Kolter & Elrod package. The project is substantially complete and now in the close out stage. 
Notes
none 
Indicator
Indicator
ID
C-155 
Project/School/Facility
Budget
$1,414,099 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Construction 
% of Phase
60% 
Project Team
Manager: Bruce Green
Architect: Courtney Harper + Partners Architects
Contractor: Job Order Contractor
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Demolition is complete in the restrooms and drywall framing has been installed. Plumbing roughin is complete. Floor preparation is underway for tile work. PA system replacement is ongoing. 
Notes
none 
Indicator
Indicator
ID
C-283 
Project/School/Facility
Budget
$1,516,381 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
1st Qtr. 2014 
Phase
Closeout 
% of Phase
65% 
Project Team
Manager: Meredith Smith
Architect: Natex Corporation
Contractor: Prime Contractors
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical systems upgrades, fire alarm upgrade, intercom replacement, markerboard replacement, flooring and fencing replacement, sitework, and ADA code compliance. 
Status
Closeout documents are being reviewed. 
Notes
none 
Indicator
Indicator
ID
C-159 
Project/School/Facility
Budget
$1,307,126 
Target Construction Start
1st Qtr. 2014 
Target Construction Completion
3rd Qtr. 2014 
Phase
Construction 
% of Phase
25% 
Project Team
Manager: Meredith Smith
Architect: PBK Architects
Contractor: Prime Contractors
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, roofing repairs, technology improvements, and ADA code compliance. 
Status
Replacement of plumbing fixtures in the Pre-K areas is underway. Scheduled door replacement has begun, door hardware has been received. Additional scope funded by Trustee allocation is being detailed. 
Notes
The project schedule has been adjusted to reflect the negotiated schedule with the awarded contractor. 
Indicator
Indicator
ID
C-262 
Project/School/Facility
Budget
$3,939,328 
Target Construction Start
3rd Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Closeout 
% of Phase
60% 
Project Team
Manager: Meredith Smith
Architect: MLB and Associates
Contractor: Prime Contractors
CMPA: AECOM Design
 
General Overview
Renovations including safety/security improvements, mechanical/electrical/plumbing system improvements, exterior doors, door hardware, restrooms upgrade, replacement of new elevator, and ADA code compliance. 
Status
Work is substantially complete and closeout documents are being prepared. Punchlist items are being corrected. 
Notes
none 
Indicator
Indicator
ID
C-049 
Project/School/Facility
Budget
$2,846,986 
Target Construction Start
4th Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Closeout 
% of Phase
40% 
Project Team
Manager: Meredith Smith
Architect: Ambrose McEnany & House Architects
Contractor: ICI Construction
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, exterior doors, door hardware, restrooms upgrade, replacement of new elevator, and ADA code compliance. 
Status
The project is substantially complete and closeout documents are being reviewed. Punch list work is ongoing. 
Notes
The original general contractor was RHJ-JOC Inc., which defaulted on their contract in December 2012. HISD has since negotiated with the surety company and contracted with a completion contractor to restart and complete the construction scope, as noted in the information section above. 
Indicator
Indicator
ID
C-169 
Project/School/Facility
Budget
$2,348,243 
Target Construction Start
4th Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Construction 
% of Phase
95% 
Project Team
Manager: Meredith Smith
Architect: Ambrose McEnany & House Architects
Contractor: ICI Construction
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, lighting, exterior, interior doors and hardware, window replacements, restrooms upgrade, fencing and ADA code compliance. 
Status
The project is substantially complete and closeout documents are being reviewed. Punch list work is ongoing. 
Notes
The original general contractor was RHJ-JOC Inc., which defaulted on their contract in December 2012. HISD has since negotiated with the surety company and contracted with a completion contractor to restart and complete the construction scope, as noted in the information section above. 
Indicator
Indicator
ID
C-053 
Project/School/Facility
Budget
$10,616,355 
Target Construction Start
1st Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Construction 
% of Phase
25% 
Project Team
Manager: Meredith Smith
Architect: English + Associates Architects
Contractor: Comex Corporation
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, new lighting, a new bus canopy, paving repairs, restroom upgrades, improved interior finishes, auditorium seating, bleachers, signage, and ADA code compliance. 
Status
Drywall framing and HVAC roughin is being completed. First floor restroom plumbing rough-in is complete and wall repair is underway. Floor repair and preparation for tile work is underway in the restrooms. HVAC and electrical work is ongoing. Abatement in the Library is complete. 
Notes
In addition to the 2007 scope of work the 2012 restroom renovation work will continue with the same project team through third quarter 2015. 
Indicator
Indicator
ID
C-050 
Project/School/Facility
Budget
$3,428,277 
Target Construction Start
4th Qtr. 2012 
Target Construction Completion
4th Qtr. 2013 
Phase
Close-Out 
% of Phase
90% 
Project Team
Manager: Bruce Green
Architect: Ambrose & House
Contractor: Prime Contractors
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements and ADA code compliance. 
Status
Construction is complete and in the closeout phase. The project is under warranty. 
Notes
none 
Indicator
Indicator
ID
C-054 
Project/School/Facility
Budget
$14,347,354 
Target Construction Start
1st Qtr. 2011 
Target Construction Completion
3rd Qtr. 2012 
Phase
Close-Out 
% of Phase
90% 
Project Team
Manager: Bruce Green
Architect: Autoarch Architects
Contractor: Summit Builders
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Closeout documents are complete. The original contractor failed to complete punch list items. A job order contractor and annual vendors are completing this work at the cost of the original contractor. 
Notes
none 
Indicator
Indicator
ID
C-182 
Project/School/Facility
Budget
$1,526,081 
Target Construction Start
1st Qtr. 2012 
Target Construction Completion
1st Qtr. 2014 
Phase
Close-Out 
% of Phase
50% 
Project Team
Manager: Meredith Smith
Architect: Corgan+PBA
Contractor: First Nat. Ins./Comex
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, restroom upgrades, roof repairs, parking lot expansion, and ADA code compliance. 
Status
Punch list work is nearing completion. 
Notes
The original general contractor was RHJ-JOC Inc., which defaulted on their contract in December 2012. HISD has since negotiated with the surety company and contracted with a completion contractor to restart and complete the construction scope, as noted in the information section above. 
Indicator
Indicator
ID
C-055 
Project/School/Facility
Budget
$10,739,621 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Construction 
% of Phase
50% 
Project Team
Manager: Bruce Green
Architect: RWS Architects
Contractor: ICI Construction
CMPA: Rice & Gardner Consultants, Inc.
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, refurbishing exterior and interior finishes, science laboratory upgrades, and ADA code compliance modifications. 
Status
An HVAC replacement package was approved by the school board in March 2014. Construction is in progress. 
Notes
Phase 1 was completed and project team is in final negotiations for close-out of the original contract. 
Indicator
Indicator
ID
C-079 
Project/School/Facility
Budget
$4,337,028 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
3rd Qtr. 2014 
Phase
Construction 
% of Phase
80% 
Project Team
Manager: Meredith Smith
Architect: Hill + Swart Architects, Inc.
Contractor: Job Order Contractor
CMPA: AECOM Design
 
General Overview
Renovations include safety/security systems improvements, mechanical/electrical/plumbing systems, fire alarm repair, intercom replacement, door and hardware replacement, science lab venting and fume hoods, sitework, construction of a fire truck access lane, and ADA code compliance. 
Status
LED light kit installation is nearing completion. Egress lighting installation is being completed. Exterior wall lights are being installed. 
Notes
none 
Indicator
Indicator
ID
C-189 
Project/School/Facility
Budget
$737,591 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
3rd Qtr. 2014 
Phase
Close-Out 
% of Phase
90% 
Project Team
Manager: Bruce Green
Architect: Cre8 Architects
Contractor: Prime Contractors
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements and ADA code compliance. 
Status
This project is in the Shearn, Kolter & Elrod package. The project is substantially complete and now in the close out stage. 
Notes
none 
Indicator
Indicator
ID
C-263 
Project/School/Facility
Budget
$1,393,085 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
3rd Qtr. 2014 
Phase
Construction 
% of Phase
50% 
Project Team
Manager: Meredith Smith
Architect: PBK Architects
Contractor: Prime Contractors
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, technology improvements, and ADA code compliance. 
Status
Window replacement is progressing with wall framing at window wall ready to start. New markerboard have been ordered. 
Notes
The project schedule has been adjusted to reflect the negotiated schedule with the awarded contractor. 
Indicator
Indicator
ID
C-128 
Project/School/Facility
Budget
$1,897,513 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
1st Qtr. 2014 
Phase
Closeout 
% of Phase
65% 
Project Team
Manager: Meredith Smith
Architect: Natex Architects
Contractor: Prime Contractors
CMPA: AECOM Design
 
General Overview
Renovations include safety/security systems improvements, mechanical and electrical systems upgrades, fire alarm upgrade, intercom replacement, marker board replacement, parking lot expansion, flooring replacement, sitework, and ADA code compliance. 
Status
Closeout documents are being reviewed. 
Notes
none 
Indicator
Indicator
ID
C-201 
Project/School/Facility
Budget
$1,042,813 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Construction 
% of Phase
98% 
Project Team
Manager: Meredith Smith
Architect: RWS Architects
Contractor: Jamail & Smith, Ohms Electric, CLS, AMS
CMPA: AECOM Design
 
General Overview
Renovations including replacing electrical system components, resolution of structural issues, door repairs, PA system and ADA code compliance, tree trimming and treatment, and masonry repairs. 
Status
The structural steel for the canopy support is being galvanized. Column footings are complete. 
Notes
none 
Indicator
Indicator
ID
C-062 
Project/School/Facility
Budget
$12,053,989 
Target Construction Start
3rd Qtr. 2012 
Target Construction Completion
3rd Qtr. 2013 
Phase
Close-Out 
% of Phase
90% 
Project Team
Manager: Bruce Green
Architect: Autoarch Architects
Contractor: Satterfield & Pontikes
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing, and ADA code compliance. This project will also include an addition to the school that features a science lab and classrooms. 
Status
Construction is complete and in the closeout phase. The project is under warranty. 
Notes
Additional egress lighting is being installed by annual vendor. 
Indicator
Indicator
ID
C-222 
Project/School/Facility
Budget
$1,040,734 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
3rd Qtr. 2014 
Phase
Construction 
% of Phase
40% 
Project Team
Manager: Bruce Green
Architect: STOA International Architects
Contractor: Jamail + Smith
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Marker/tack boards in all classrooms and replacement exterior doors have been ordered. Marquee sign has been ordered and power is in place. The exterior and site lighting package is being priced. 
Notes
none 
Indicator
Indicator
ID
C-223 
Project/School/Facility
Budget
$3,038,220 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Construction 
% of Phase
15% 
Project Team
Manager: Bruce Green
Architect: RdlR Architects
Contractor: Level Infrastructure, LLC
CMPA: AECOM Design
 
General Overview
Renovations, including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Abatement in the Pre-K area is underway. Demolition in the administration area is complete. Exterior canopy walk demolition is underway. 
Notes
none 
Indicator
Indicator
ID
C-060 
Project/School/Facility
Budget
$1,758,507 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Construction 
% of Phase
95% 
Project Team
Manager: Bruce Green
Architect: Sustaita Architects
Contractor: DT Construction
CMPA: Rice & Gardner
 
General Overview
Renovations including Replacement of storefronts; floor finishes (VCT, ceramic); ceiling finishes (acoustical tile); science classroom millwork; wall finishes (Paint, ceramic tile); masonry (CMU); restroom partitions, plumbing and fixture upgrades; exhaust fan additions; exterior lighting; site work. 
Status
The new flooring, science classroom, and first floor restroom renovations are complete. The second floor restroom renovations and selected window and door replacements have been completed. 
Notes
In addition to the 2007 scope of work the 2012 restroom renovation work has been added and will be completed with the same project team. 
Indicator
Indicator
ID
C-039 
Project/School/Facility
Budget
$7,652,171 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Construction 
% of Phase
90% 
Project Team
Manager: Bruce Green
Architect: Sustaita Architects
Contractor: DT Construction
CMPA: Rice & Gardner Consultants, Inc.
 
General Overview
Renovations including storefront and curtain wall replacement, HVAC replacement and repairs, electrical panel replacement, electrical upgrades, door and window replacement, ceramic tile floor and carpet replacement, restroom renovations, plumbing fixture replacements, drinking fountain additions, millwork upgrades, suspended ceiling repairs and replacement, abatement, PA additions and signage. 
Status
Cafeteria, gymnasium, and library renovations are complete along with the 1st floor restrooms. The restroom renovations, HVAC upgrades, and select window and door replacement are ongoing. 
Notes
In addition to the 2007 scope of work additional restroom renovations work was added to accommodate the special needs of this school. This additional scope will be completed late second quarter 2014. 
Indicator
Indicator
ID
C-232 
Project/School/Facility
Budget
$3,859,075 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
3rd Qtr. 2014 
Phase
Construction 
% of Phase
40% 
Project Team
Manager: Meredith Smith
Architect: Harrison Kornberg Architects
Contractor: Job Order Contractor
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, roof repairs, restrooms upgrade, science laboratory upgrades, elevator installation, and ADA code compliance. 
Status
Restroom painting samples are being reviewed. Plumbing fixtures are being renovated. Site lighting is progressing. Floor prep and plumbing rough-in is complete in the restrooms. New corridor light fixtures have been delivered and the replacement HVAC unit for the kitchen is being priced. 
Notes
none 
Indicator
Indicator
ID
C-234 
Project/School/Facility
Budget
$11,472,363 
Target Construction Start
1st Qtr. 2013 
Target Construction Completion
2nd Qtr. 2014 
Phase
Closeout 
% of Phase
50% 
Project Team
Manager: Bruce Green
Architect: STOA International Architects
Contractor: Satterfield & Pontikes
CMPA: Rice & Gardner Consultants, Inc
 
General Overview
A middle school addition and renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
The school has moved into the new addition. Final site work, punch list and closeout is ongoing. 
Notes
A separate roof project is anticipated to be presented for approval to the school board in April 2014, with construction scheduled to occur through the third quarter 2014. 
Indicator
Indicator
ID
C-281 
Project/School/Facility
Budget
$837,414 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
3rd Qtr. 2014 
Phase
Construction 
% of Phase
60% 
Project Team
Manager: Bruce Green
Architect: Courtney Harper + Partners Architects
Contractor: Job Order Contractor
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements and ADA compliance. 
Status
Exterior lighting replacement is underway and replacement door materials have been ordered. Restroom plumbing rough-in and wall framing is complete and floor preparation for new finishes is underway. 
Notes
none 
Indicator
Indicator
ID
C-239 
Project/School/Facility
Budget
$2,479,845 
Target Construction Start
2nd Qtr. 2013 
Target Construction Completion
4th Qtr. 2013 
Phase
Close-Out 
% of Phase
90% 
Project Team
Manager: Bruce Green
Architect: Cre8 Architects
Contractor: Prime Contractors
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, site work, exterior and interior finishes, technology systems improvements, and ADA code compliance. 
Status
This project is in the Shearn, Kolter & Elrod package. The project is substantially complete and now in the close out stage. 
Notes
none 
Indicator
Indicator
ID
C-240 
Project/School/Facility
Budget
$18,189,731 
Target Construction Start
3rd Qtr. 2012 
Target Construction Completion
4th Qtr. 2013 
Phase
Close-Out 
% of Phase
90% 
Project Team
Manager: Travis Stanford
Architect: Collaborate
Contractor: Comex Corporation
CMPA: N/A
 
General Overview
New school for 750 students. 
Status
Construction is complete and is in the warranty phase. Certificate of Occupancy has been obtained. The campus occupied the new facility fourth quarter 2013. Final documentation is in progress for LEED certification. 
Notes
none 
Indicator
Indicator
ID
C-242 
Project/School/Facility
Budget
$17,050,846 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Construction: Final Phase 
% of Phase
5% 
Project Team
Manager: Travis Stanford
Architect: Brave Architecture
Contractor: Comex Corporation
CMPA: N/A
 
General Overview
School expansion. 
Status
The school moved into the new classroom/administrative wing of the building in fall 2013. Changes for the library and cafeteria (Phase 2) plans have been approved by the City of Houston and construction started on the parking lot in May 2014 with the goal of having it ready for use by the start of the Fall semester 2014. 
Notes
The additional scope of work, including the library and cafeteria will be completed second quarter 2015. 
Indicator
Indicator
ID
C-244 
Project/School/Facility
Budget
$12,947,996 
Target Construction Start
3rd Qtr. 2012 
Target Construction Completion
2nd Qtr. 2014 
Phase
Construction 
% of Phase
85% 
Project Team
Manager: Bruce Green
Architect: Collaborate Architects
Contractor: Morganti Construction
CMPA: Rice & Gardner Consultants, Inc.
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. This project will include two additions to the school, a new multi-purpose building and a new Administration/Library wing. An additional project to replace the roof is currently planned for the third quarter 2014. 
Status
The construction of the new Library/Administration wing and Multi-Purpose Building is complete. Site work and Phases 5 & 6 are underway. 
Notes
A separate roof project is anticipated to be presented for approval to the school board in April 2014, with construction scheduled to occur through the third quarter 2014. 
Indicator
Indicator
ID
C-098 
Project/School/Facility
Budget
$3,230,362 
Target Construction Start
2nd Qtr. 2012 
Target Construction Completion
4th Qtr. 2013 
Phase
Close-Out 
% of Phase
90% 
Project Team
Manager: Bruce Green
Architect: RWS Architects
Contractor: Prime Contractors
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Construction is complete and in the closeout phase. The project is under warranty. 
Notes
none 
Indicator
Indicator
ID
C-248 
Project/School/Facility
Budget
$6,310,699 
Target Construction Start
1st Qtr. 2012 
Target Construction Completion
4th Qtr. 2013 
Phase
Close-Out 
% of Phase
90% 
Project Team
Manager: Bruce Green
Architect: Pfluger Associates
Contractor: Solidarity / Jamail & Smith
CMPA: Rice & Gardner
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, exterior finishes, and ADA code compliance. 
Status
Minor punch list items are remaining to be completed. The HVAC replacement work is complete. Project is substantially complete. 
Notes
none 
Indicator
Indicator
ID
C-252 
Project/School/Facility
Budget
$3,177,976 
Target Construction Start
1st Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Construction 
% of Phase
55% 
Project Team
Manager: Meredith Smith
Architect: RWS Architects
Contractor: Comex Corporation
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, replacing lighting, flooring, casework, ceilings in classrooms, revising admin area, new PA building alarm and fire alarm system. 
Status
Window replacement is nearing completion in all areas. Wall framing and ceiling insulation is underway in the administration area. New ceiling installation and light fixture rough-in in the classrooms is starting. The Clinic plumbing work is underway. 
Notes
none 
Indicator
Indicator
ID
C-258 
Project/School/Facility
Budget
$3,712,925 
Target Construction Start
4th Qtr. 2013 
Target Construction Completion
3rd Qtr. 2014 
Phase
Construction 
% of Phase
95% 
Project Team
Manager: Chris Koeper
Architect: Prozign Architects
Contractor: ICI Construction
CMPA: N/A
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, and ADA code compliance. 
Status
Renovation and interior finishes are ongoing, including the elevator installation and misc. long lead items. Low voltage systems will be complete by third quarter 2014. 
Notes
The original schedule was to start construction second quarter 2012 with an anticipated completion being first quarter 2013. The general contractor was RHJ-JOC Inc., which defaulted on their contract in December 2012. HISD has since negotiated with the surety company and contracted with a completion contractor to restart and complete the construction scope, as noted in the information section above. 
Indicator
Indicator
ID
C-260 
Project/School/Facility
Budget
$3,973,214 
Target Construction Start
2nd Qtr. 2014 
Target Construction Completion
4th Qtr. 2014 
Phase
Construction 
% of Phase
20% 
Project Team
Manager: Meredith Smith
Architect: VLK Architects
Contractor: Renovation — Patriot Construction; Window Replacement — Jamail & Smith
CMPA: AECOM Design
 
General Overview
Renovations including safety/security systems improvements, mechanical/electrical/plumbing systems improvements, interior and exterior finishes, windows, technology improvements, and ADA code compliance. 
Status
Window replacement is underway with abatement nearing completion. Restroom demolition is complete and wall framing is on-going. New exterior doors, markerboards, and toilet partitions have been ordered. Phase 2, which will include mechanical system replacement, is in design and is scheduled for completion by 3rd quarter 2015. 
Notes
none 

Last Updated: 12/13/2013