• Traffic Light Report

    The Traffic Lights represent the following:
    Indicator
    • Green light indicates the project is on schedule and on budget--there are no pending issues of concern.
    • Yellow light indicates a project may have budget or schedule concerns--there are issues that bear monitoring.
    • Red light indicates a project has significant budget and/or schedule concerns--there are issues to be addressed.
    Traffic Light Report to reflect project status for the 2nd quarter of 2017.
    Indicator
    Indicator
    ID
    C-274 
    Project/School/Facility
    Budget
    $26,632,000 
    Planning and Design Start
    Early/Mid 2015 
    Construction Start
    Mid/Late 2016 
    Phase
    Construction 
    % of Phase
    45% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Cre8 Architects
    Contractor: Drymalla Construction
    Program Mgr: Rice & Gardner Consultants, Inc.
     
    General Overview
    New school for 850 students. 
    Status
    MEP rough-in and interior wall framing are ongoing. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-001 
    Project/School/Facility
    Budget
    $68,429,000 
    Planning and Design Start
    Late 2015/Early 2016 
    Construction Start
    Late 2016 
    Phase
    Construction 
    % of Phase
    1% 
    Project Team
    HISD Mgr: Dan Bankhead
    Architect: ERO Architects
    Contractor: Pepper-Lawson Construction, LP
    Program Mgr: Heery International, Inc.
     
    General Overview
    New facility preserving the architecturally significant building structure for a campus accommodating 1,800-2,000 students. 
    Status
    Temporary campus work has commenced. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-002 
    Project/School/Facility
    Budget
    $106,724,000 
    Planning and Design Start
    Early/Mid 2014 
    Construction Start
    TBD 
    Phase
    Schematic Design 
    % of Phase
    65% 
    Project Team
    HISD Mgr: Dan Bankhead
    Architect: PBK Architects
    Contractor: Turner Construction
    Program Mgr: Heery International
     
    General Overview
    New school for 2,800 – 3,100 students that will incorporate the recently completed science classroom and laboratory wing. 
    Status
    Schematic design ongoing. 
    Notes
    None 
    Indicator
    Indicator
    ID
    C-130 
    Project/School/Facility
    Budget
    $24,293,919 
    Planning and Design Start
    Early/Mid 2013 
    Construction Start
    Mid/Late 2014 
    Phase
    Closeout 
    % of Phase
    80% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: VLK Architects
    Contractor: DivisionOne
    Program Mgr: Heery International
     
    General Overview
    New school for 750 students. 
    Status
    Closeout underway. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-026 
    Project/School/Facility
    Budget
    $64,512,000 
    Planning and Design Start
    Early/Mid 2013 
    Construction Start
    Mid/Late 2014 
    Phase
    Closeout 
    % of Phase
    75% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: WHR/Lake Flato
    Contractor: Tellepsen Builders
    Program Mgr: Heery International
     
    General Overview
    New school for 900-1,000 students. 
    Status
    Closeout underway. 
    Notes
    None 
    Indicator
    Indicator
    ID
    C-301 
    Project/School/Facility
    Budget
    $10,875,000 
    Planning and Design Start
    Early/Mid 2014 
    Construction Start
    Early/Mid 2016 
    Phase
    Construction 
    % of Phase
    76% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Prozign
    Contractor: Patriot Contracting, LLC
    Program Mgr: Rice & Gardner
     
    General Overview
    New facility that will incorporate the new 2 story classroom wing for a campus accommodating 500 students. 
    Status
    Exterior envelope, overhead MEP, and drywall framing are ongoing. 
    Notes
    None 
    Indicator
    Indicator
    ID
    C-004 
    Project/School/Facility
    Budget
    $55,100,000 
    Planning and Design Start
    Early/Mid 2013 
    Construction Start
    Mid/Late 2015 
    Phase
    Construction 
    % of Phase
    99% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: ERO Architects
    Contractor: Prime Contractors
    Program Mgr: Rice & Gardner
     
    General Overview
    New high school to accommodate 1,000 - 1,300 students. 
    Status
    Crews are preparing for demolition of old school. Project closeout ongoing. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-157 
    Project/School/Facility
    Budget
    $26,678,000 
    Planning and Design Start
    Late 2015/Early 2016 
    Construction Start
    Mid/Late 2016 
    Phase
    Construction 
    % of Phase
    42% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Hill Swart Chu Architects, LLC
    Contractor: B3Ci
    Program Mgr: Rice & Gardner Consultants, Inc.
     
    General Overview
    New addition and general renovations of the existing facilities to accommodate 750-900 students. 
    Status
    Exterior envelope and overhead MEP for building addition are ongoing. Kitchen quarry tile installation also is ongoing. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-034 
    Project/School/Facility
    Budget
    $39,998,131 
    Planning and Design Start
    Early/Mid 2014 
    Construction Start
    Early/Mid 2016 
    Phase
    Construction 
    % of Phase
    68% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Page | DLR
    Contractor: B3Ci
    Program Mgr: Rice & Gardner
     
    General Overview
    The school will be rebuilt and funded from surplus bond monies or from real estate sale proceeds. 
    Status
    Exterior envelope, overhead MEP, and drywall installation are ongoing. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-025 
    Project/School/Facility
    Budget
    $80,178,000 
    Planning and Design Start
    Early/Mid 2013 
    Construction Start
    Early/Mid 2016 
    Phase
    Construction 
    % of Phase
    63% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Gensler
    Contractor: McCarthy
    Program Mgr: Rice & Gardner
     
    General Overview
    New performing and visual arts school to accommodate 750 students. 
    Status
    MEP rough-in, CMU interior walls, and interior wall framing are ongoing. 
    Notes
    None 
    Indicator
    Indicator
    ID
    C-006 
    Project/School/Facility
    Budget
    $1,125,000 
    Planning and Design Start
    Late 2015/Early 2016 
    Construction Start
    Mid 2016 
    Phase
    Closeout 
    % of Phase
    55% 
    Project Team
    HISD Mgr: Dan Bankhead
    Architect: N/A
    Contractor: P2MG
    Program Mgr: N/A
     
    General Overview
    Renovations to existing school facilities. 
    Status
    Closeout is ongoing. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-033 
    Project/School/Facility
    Budget
    $36,693,000 
    Planning and Design Start
    Early/Mid 2015 
    Construction Start
    Mid/Late 2016 
    Phase
    Construction 
    % of Phase
    7% 
    Project Team
    HISD Mgr: Dan Bankhead
    Architect: Corgan Associates, Inc. dba Corgan
    Contractor: Cadence McShane
    Program Mgr: Heery International, Inc.
     
    General Overview
    New school for 600-800 students. 
    Status
    Foundation work is ongoing. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-007 
    Project/School/Facility
    Budget
    $17,000,000 
    Planning and Design Start
    Late 2015/Early 2016 
    Construction Start
    Early/Mid 2016 
    Phase
    Construction 
    % of Phase
    98% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Natex Corporation
    Contractor: DT Construction
    Program Mgr: URS - Skanska
     
    General Overview
    Renovations to existing school facilities and site improvements. 
    Status
    Interior finishes are ongoing in the building addition. Lab casework installation is ongoing in science labs. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-008 
    Project/School/Facility
    Budget
    $107,974,000 
    Planning and Design Start
    Early/Mid 2014 
    Construction Start
    Early/Mid 2016 
    Phase
    Construction 
    % of Phase
    20% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Perkins-Will
    Contractor: Gilbane Building Co
    Program Mgr: Heery International
     
    General Overview
    New facility preserving the architecturally significant building structure for a campus accommodating 2,800 – 3,100 students. 
    Status
    Drilled piers are ongoing. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-075 
    Project/School/Facility
    Budget
    $59,125,000 
    Planning and Design Start
    Early/Mid 2014 
    Construction Start
    Early/Mid 2016 
    Phase
    Construction 
    % of Phase
    65% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Harrison Kornberg
    Contractor: Turner Construction
    Program Mgr: Rice & Gardner
     
    General Overview
    New school for 1,300-1,500 students. 
    Status
    Exterior envelope, overhead MEP, and drywall framing are ongoing. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-010 
    Project/School/Facility
    Budget
    $82,736,000 
    Planning and Design Start
    Late 2015/Early 2016 
    Construction Start
    Late 2016 
    Phase
    Construction 
    % of Phase
    19% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Morris Architects, Inc.
    Contractor: Satterfield and Pontikes Construction, Inc.
    Program Mgr: Heery International, Inc.
     
    General Overview
    New school for 1,900-2,100 students that will incorporate recent science and classroom building renovations. 
    Status
    Tilt wall panel erection ongoing. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-460 
    Project/School/Facility
    Budget
    $32,161,000 
    Planning and Design Start
    Early/Mid 2013 
    Construction Start
    Mid/Late 2014 
    Phase
    Closeout 
    % of Phase
    80% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: PBK Architects
    Contractor: Satterfield & Pontikes
    Program Mgr: Heery International
     
    General Overview
    New school for 750-900 students. 
    Status
    Project closeout ongoing. 
    Notes
    none 
    Indicator
    Indicator
    ID
    NA 
    Project/School/Facility
    Budget
    $23,417,000 
    Planning and Design Start
    Early/Mid 2013 
    Construction Start
    Mid/Late 2014 
    Phase
    Closeout 
    % of Phase
    25% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: English & Associates
    Contractor: DivisionOne
    Program Mgr: Rice Gardner
     
    General Overview
    New school for 750 students. 
    Status
    Project closeout ongoing. 
    Notes
     
    Indicator
    Indicator
    ID
    C-067 
    Project/School/Facility
    Budget
    $42,402,000 
    Planning and Design Start
    Early/Mid 2013 
    Construction Start
    Mid/Late 2014 
    Phase
    Closeout 
    % of Phase
    5% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Harrison Kornberg
    Contractor: Prime Contractors
    Program Mgr: Rice & Gardner
     
    General Overview
    New facility for a campus accommodating 900 – 1,000 students. 
    Status
    Project closeout ongoing. 
    Notes
    None 
    Indicator
    Indicator
    ID
    C-011 
    Project/School/Facility
    Budget
    $68,810,000 
    Planning and Design Start
    Early/Mid 2013 
    Construction Start
    Mid/Late 2014 
    Phase
    Closeout 
    % of Phase
    50% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Kirksey
    Contractor: Tellepsen Builders
    Program Mgr: Heery International
     
    General Overview
    New school preserving the architecturally significant building structure to accommodate 1,800 – 2,000 students. 
    Status
    Project closeout ongoing. 
    Notes
    None 
    Indicator
    Indicator
    ID
    C-308 
    Project/School/Facility
    Budget
    $13,500,000 
    Planning and Design Start
    Early/Mid 2013 
    Construction Start
    Mid/Late 2014 
    Phase
    Closeout 
    % of Phase
    100% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: RdlR Architects
    Contractor: Drymalla
    Program Mgr: Kwame Bldg Grp
     
    General Overview
    New school for 400 students at the Houston Community College – Northline Campus. 
    Status
    Complete 
    Notes
     
    Indicator
    Indicator
    ID
    C-003 
    Project/School/Facility
    Budget
    $46,764,000 
    Planning and Design Start
    Early/Mid 2014 
    Construction Start
    Mid/Late 2015 
    Phase
    Construction 
    % of Phase
    16% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Bay – IBI
    Contractor: Satterfield & Pontikes
    Program Mgr: Heery International
     
    General Overview
    New facility preserving the architecturally significant building structure for a school accommodating 1,500 – 1,700 students. 
    Status
    Structural steel for culinary addition is underway. Bus loop is complete. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-215 
    Project/School/Facility
    Budget
    $29,485,000 
    Planning and Design Start
    Early/Mid 2014 
    Construction Start
    Early/Mid 2016 
    Phase
    Construction 
    % of Phase
    50% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Brave Architecture
    Contractor: Patriot Contracting
    Program Mgr: URS-Skanska
     
    General Overview
    New school for 850 students. 
    Status
    Exterior envelope, overhead MEP, and drywall framing are ongoing. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-218 
    Project/School/Facility
    Budget
    $7,989,000 
    Planning and Design Start
    Late 2015/Early 2016 
    Construction Start
    Mid 2016 
    Phase
    Construction 
    % of Phase
    20% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: RDC Architects, PLLC
    Contractor: DT Construction
    Program Mgr: Heery International, Inc.
     
    General Overview
    New addition for a campus accommodating 750 – 900 students. 
    Status
    Building foundation is ongoing. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-310 
    Project/School/Facility
    Budget
    $101,428,000 
    Planning and Design Start
    Early/Mid 2015 
    Construction Start
    Mid/Late 2016 
    Phase
    Construction 
    % of Phase
    20% 
    Project Team
    HISD Mgr: Dan Bankhead
    Architect: Stantec Architecture, Inc.
    Contractor: Satterfield & Pontikes Construction, Inc.
    Program Mgr: URS - Skanska
     
    General Overview
    New school that incorporates the new science classroom and laboratory wing for 2,550-2,750 students. 
    Status
    Building foundation work and tilt wall panel erection are ongoing. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-024 
    Project/School/Facility
    Budget
    $12,566,000 
    Planning and Design Start
    Late 2015/Early 2016 
    Construction Start
    Mid/Late 2016 
    Phase
    Construction 
    % of Phase
    57% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Randall - Porterfield Architects, Inc.
    Contractor: DT Construction
    Program Mgr: URS - Skanska
     
    General Overview
    Renovations to existing school facilities and site improvements. 
    Status
    Exterior envelope and overhead MEP are ongoing for the JROTC/Performing Arts building. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-023 
    Project/School/Facility
    Budget
    $54,944,000 
    Planning and Design Start
    Early/Mid 2013 
    Construction Start
    Mid/Late 2014 
    Phase
    Construction 
    % of Phase
    78% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Kell-Munoz Co.
    Contractor: ICI Construction
    Program Mgr: URS - Skanska
     
    General Overview
    New school for 1,300-1,500 students. 
    Status
    Interior finishes are ongoing. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-081 
    Project/School/Facility
    Budget
    $6,125,000 
    Planning and Design Start
    Late 2015/Early 2016 
    Construction Start
    Early/Mid 2016 
    Phase
    Closeout 
    % of Phase
    10% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Autoarch Architects, Inc.
    Contractor: DT Construction
    Program Mgr: Rice & Gardner Consultants, Inc.
     
    General Overview
    Project closeout ongoing. 
    Status
    Closeout 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-454 
    Project/School/Facility
    Budget
    $13,500,000 
    Planning and Design Start
    Early/Mid 2013 
    Construction Start
    Mid/Late 2014 
    Phase
    Closeout 
    % of Phase
    100% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Smith & Co. Architects
    Contractor: Drymalla
    Program Mgr: N/A
     
    General Overview
    New school for 400 students at the Houston Community College – South Campus. 
    Status
    Complete 
    Notes
    None 
    Indicator
    Indicator
    ID
    C-014 
    Project/School/Facility
    Budget
    $72,304,000 
    Planning and Design Start
    Early/Mid 2013 
    Construction Start
    Mid/Late 2014 
    Phase
    Closeout 
    % of Phase
    50% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: SHW Group
    Contractor: Cadence McShane
    Program Mgr: Heery International
     
    General Overview
    New school for 1,600 – 1,800 students. 
    Status
    Project closeout ongoing. 
    Notes
    None 
    Indicator
    Indicator
    ID
    C-068 
    Project/School/Facility
    Budget
    $14,825,000 
    Planning and Design Start
    Early/Mid 2013 
    Construction Start
    Mid/Late 2014 
    Phase
    Closeout 
    % of Phase
    100% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Natex Architects
    Contractor: DivisionOne
    Program Mgr: Rice & Gardner
     
    General Overview
    New addition to complete multi-phase master plan for the campus. 
    Status
    Complete 
    Notes
    None 
    Indicator
    Indicator
    ID
    C-015 
    Project/School/Facility
    Budget
    $30,115,000 
    Planning and Design Start
    Early/Mid 2013 
    Construction Start
    Mid/Late 2014 
    Phase
    Closeout 
    % of Phase
    5% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Gensler
    Contractor: Satterfield & Pontikes
    Program Mgr: Rice Gardner
     
    General Overview
    Partial replacement and general renovations to accommodate 1,800-2,000 students. 
    Status
    Project closeout ongoing. 
    Notes
    None 
    Indicator
    Indicator
    ID
    C-016 
    Project/School/Facility
    Budget
    $51,732,000 
    Planning and Design Start
    Early/Mid 2013 
    Construction Start
    Mid/Late 2014 
    Phase
    Construction 
    % of Phase
    71% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Fanning-Howey/House Partners
    Contractor: Prime Contractors
    Program Mgr: N/A
     
    General Overview
    New school for 1,100-1,300 students. 
    Status
    Exterior envelope, overhead MEP, and drywall framing are ongoing. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-017 
    Project/School/Facility
    Budget
    $40,006,000 
    Planning and Design Start
    Late 2015/Early 2016 
    Construction Start
    Late 2016 
    Phase
    Construction 
    % of Phase
    68% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Joiner Partnership, Inc.
    Contractor: Satterfield & Pontikes Construction, Inc.
    Program Mgr: Rice & Gardner Consultants, Inc.
     
    General Overview
    Partial replacement and general renovations to accommodate 2,300-2,500 students. 
    Status
    Exterior envelope, overhead MEP, and drywall framing are ongoing. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-256 
    Project/School/Facility
    Budget
    $35,603,000 
    Planning and Design Start
    Late 2015/Early 2016 
    Construction Start
    Late 2016 
    Phase
    Construction 
    % of Phase
    23% 
    Project Team
    HISD Mgr: Dan Bankhead
    Architect: H. Munoz & Company, Inc.
    Contractor: DivisionOne Construction
    Program Mgr: Heery International, Inc.
     
    General Overview
    New addition and general renovations of the existing facilities to accommodate 750-900 students. 
    Status
    Building foundation is ongoing. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-259 
    Project/School/Facility
    Budget
    $18,914,000 
    Planning and Design Start
    Late 2015/Early 2016 
    Construction Start
    Late 2016 
    Phase
    Construction 
    % of Phase
    43% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Smith & Company Architects, Inc.
    Contractor: Drymalla Construction Co.
    Program Mgr: Rice & Gardner Consultants, Inc.
     
    General Overview
    New addition and general renovations to accommodate 750-900 students. 
    Status
    Masonry, overhead MEP, and drywall installation are ongoing. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-009 
    Project/School/Facility
    Budget
    $73,801,000 
    Planning and Design Start
    Early/Mid 2013 
    Construction Start
    Mid/Late 2014 
    Phase
    Closeout 
    % of Phase
    5% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: WHR & Lake|Flato
    Contractor: Satterfield & Pontikes
    Program Mgr: URS - Skanska
     
    General Overview
    New school for 1,700-1,900 students. 
    Status
    Project closeout ongoing. 
    Notes
    None 
    Indicator
    Indicator
    ID
    C-019 
    Project/School/Facility
    Budget
    $30,180,000 
    Planning and Design Start
    Early/Mid 2013 
    Construction Start
    Mid/Late 2014 
    Phase
    Construction 
    % of Phase
    20% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Molina Walker
    Contractor: B3Ci
    Program Mgr: N/A
     
    General Overview
    New facility that will incorporate the new two-story classroom wing for a campus accommodating 1,100 – 1,300 students. 
    Status
    Foundation work is ongoing. 
    Notes
    None 
    Indicator
    Indicator
    ID
    C-020 
    Project/School/Facility
    Budget
    $59,481,000 
    Planning and Design Start
    Early/Mid 2014 
    Construction Start
    Mid/Late 2015 
    Phase
    Construction 
    % of Phase
    50% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Moody Nolan
    Contractor: Turner Construction
    Program Mgr: N/A
     
    General Overview
    New school for 1,300-1,500 students. 
    Status
    Exterior envelope, overhead MEP, and drywall framing are ongoing. 
    Notes
    none 
    Indicator
    Indicator
    ID
    C-029 
    Project/School/Facility
    Budget
    $27,159,000 
    Planning and Design Start
    Early/Mid 2015 
    Construction Start
    Mid/Late 2016 
    Phase
    Construction 
    % of Phase
    60% 
    Project Team
    HISD Mgr: Andreas Peeples
    Architect: Natex Corporation
    Contractor: Satterfield & Pontikes Construction, Inc.
    Program Mgr: Heery International, Inc.
     
    General Overview
    Partial replacement and general renovations for a campus accommodating 900-1,000 students. 
    Status
    Building addition is complete and in use. Renovation work is ongoing. 
    Notes
    none