Traffic Light Report
The Traffic Lights represent the following:- Green light indicates the project is on schedule and on budget--there are no pending issues of concern.
- Yellow light indicates a project may have budget or schedule concerns--there are issues that bear monitoring.
- Red light indicates a project has significant budget and/or schedule concerns--there are issues to be addressed.
Traffic Light Report to reflect project status for the 2nd quarter of 2017.IndicatorPlanning and Design StartEarly/Mid 2015Construction StartMid/Late 2016PhaseConstruction% of Phase45%Project TeamHISD Mgr: Andreas PeeplesArchitect: Cre8 ArchitectsContractor: Drymalla ConstructionProgram Mgr: Rice & Gardner Consultants, Inc.General OverviewNew school for 850 students.StatusMEP rough-in and interior wall framing are ongoing.NotesnoneIndicatorPlanning and Design StartLate 2015/Early 2016Construction StartLate 2016PhaseConstruction% of Phase1%Project TeamHISD Mgr: Dan BankheadArchitect: ERO ArchitectsContractor: Pepper-Lawson Construction, LPProgram Mgr: Heery International, Inc.General OverviewNew facility preserving the architecturally significant building structure for a campus accommodating 1,800-2,000 students.StatusTemporary campus work has commenced.NotesnoneIndicatorPlanning and Design StartEarly/Mid 2014Construction StartTBDPhaseSchematic Design% of Phase65%Project TeamHISD Mgr: Dan BankheadArchitect: PBK ArchitectsContractor: Turner ConstructionProgram Mgr: Heery InternationalGeneral OverviewNew school for 2,800 – 3,100 students that will incorporate the recently completed science classroom and laboratory wing.StatusSchematic design ongoing.NotesNoneIndicatorPlanning and Design StartEarly/Mid 2013Construction StartMid/Late 2014PhaseCloseout% of Phase80%Project TeamHISD Mgr: Andreas PeeplesArchitect: VLK ArchitectsContractor: DivisionOneProgram Mgr: Heery InternationalGeneral OverviewNew school for 750 students.StatusCloseout underway.NotesnoneIndicatorPlanning and Design StartEarly/Mid 2013Construction StartMid/Late 2014PhaseCloseout% of Phase75%Project TeamHISD Mgr: Andreas PeeplesArchitect: WHR/Lake FlatoContractor: Tellepsen BuildersProgram Mgr: Heery InternationalGeneral OverviewNew school for 900-1,000 students.StatusCloseout underway.NotesNoneIndicatorPlanning and Design StartEarly/Mid 2014Construction StartEarly/Mid 2016PhaseConstruction% of Phase76%Project TeamHISD Mgr: Andreas PeeplesArchitect: ProzignContractor: Patriot Contracting, LLCProgram Mgr: Rice & GardnerGeneral OverviewNew facility that will incorporate the new 2 story classroom wing for a campus accommodating 500 students.StatusExterior envelope, overhead MEP, and drywall framing are ongoing.NotesNoneIndicatorPlanning and Design StartEarly/Mid 2013Construction StartMid/Late 2015PhaseConstruction% of Phase99%Project TeamHISD Mgr: Andreas PeeplesArchitect: ERO ArchitectsContractor: Prime ContractorsProgram Mgr: Rice & GardnerGeneral OverviewNew high school to accommodate 1,000 - 1,300 students.StatusCrews are preparing for demolition of old school. Project closeout ongoing.NotesnoneIndicatorPlanning and Design StartLate 2015/Early 2016Construction StartMid/Late 2016PhaseConstruction% of Phase42%Project TeamHISD Mgr: Andreas PeeplesArchitect: Hill Swart Chu Architects, LLCContractor: B3CiProgram Mgr: Rice & Gardner Consultants, Inc.General OverviewNew addition and general renovations of the existing facilities to accommodate 750-900 students.StatusExterior envelope and overhead MEP for building addition are ongoing. Kitchen quarry tile installation also is ongoing.NotesnoneIndicatorPlanning and Design StartEarly/Mid 2014Construction StartEarly/Mid 2016PhaseConstruction% of Phase68%Project TeamHISD Mgr: Andreas PeeplesArchitect: Page | DLRContractor: B3CiProgram Mgr: Rice & GardnerGeneral OverviewThe school will be rebuilt and funded from surplus bond monies or from real estate sale proceeds.StatusExterior envelope, overhead MEP, and drywall installation are ongoing.NotesnoneIndicatorPlanning and Design StartEarly/Mid 2013Construction StartEarly/Mid 2016PhaseConstruction% of Phase63%Project TeamHISD Mgr: Andreas PeeplesArchitect: GenslerContractor: McCarthyProgram Mgr: Rice & GardnerGeneral OverviewNew performing and visual arts school to accommodate 750 students.StatusMEP rough-in, CMU interior walls, and interior wall framing are ongoing.NotesNoneIndicatorPlanning and Design StartLate 2015/Early 2016Construction StartMid 2016PhaseCloseout% of Phase55%Project TeamHISD Mgr: Dan BankheadArchitect: N/AContractor: P2MGProgram Mgr: N/AGeneral OverviewRenovations to existing school facilities.StatusCloseout is ongoing.NotesnoneIndicatorPlanning and Design StartEarly/Mid 2015Construction StartMid/Late 2016PhaseConstruction% of Phase7%Project TeamHISD Mgr: Dan BankheadArchitect: Corgan Associates, Inc. dba CorganContractor: Cadence McShaneProgram Mgr: Heery International, Inc.General OverviewNew school for 600-800 students.StatusFoundation work is ongoing.NotesnoneIndicatorPlanning and Design StartLate 2015/Early 2016Construction StartEarly/Mid 2016PhaseConstruction% of Phase98%Project TeamHISD Mgr: Andreas PeeplesArchitect: Natex CorporationContractor: DT ConstructionProgram Mgr: URS - SkanskaGeneral OverviewRenovations to existing school facilities and site improvements.StatusInterior finishes are ongoing in the building addition. Lab casework installation is ongoing in science labs.NotesnoneIndicatorPlanning and Design StartEarly/Mid 2014Construction StartEarly/Mid 2016PhaseConstruction% of Phase20%Project TeamHISD Mgr: Andreas PeeplesArchitect: Perkins-WillContractor: Gilbane Building CoProgram Mgr: Heery InternationalGeneral OverviewNew facility preserving the architecturally significant building structure for a campus accommodating 2,800 – 3,100 students.StatusDrilled piers are ongoing.NotesnoneIndicatorPlanning and Design StartEarly/Mid 2014Construction StartEarly/Mid 2016PhaseConstruction% of Phase65%Project TeamHISD Mgr: Andreas PeeplesArchitect: Harrison KornbergContractor: Turner ConstructionProgram Mgr: Rice & GardnerGeneral OverviewNew school for 1,300-1,500 students.StatusExterior envelope, overhead MEP, and drywall framing are ongoing.NotesnoneIndicatorPlanning and Design StartLate 2015/Early 2016Construction StartLate 2016PhaseConstruction% of Phase19%Project TeamHISD Mgr: Andreas PeeplesArchitect: Morris Architects, Inc.Contractor: Satterfield and Pontikes Construction, Inc.Program Mgr: Heery International, Inc.General OverviewNew school for 1,900-2,100 students that will incorporate recent science and classroom building renovations.StatusTilt wall panel erection ongoing.NotesnoneIndicatorPlanning and Design StartEarly/Mid 2013Construction StartMid/Late 2014PhaseCloseout% of Phase80%Project TeamHISD Mgr: Andreas PeeplesArchitect: PBK ArchitectsContractor: Satterfield & PontikesProgram Mgr: Heery InternationalGeneral OverviewNew school for 750-900 students.StatusProject closeout ongoing.NotesnoneIndicatorPlanning and Design StartEarly/Mid 2013Construction StartMid/Late 2014PhaseCloseout% of Phase25%Project TeamHISD Mgr: Andreas PeeplesArchitect: English & AssociatesContractor: DivisionOneProgram Mgr: Rice GardnerGeneral OverviewNew school for 750 students.StatusProject closeout ongoing.NotesIndicatorPlanning and Design StartEarly/Mid 2013Construction StartMid/Late 2014PhaseCloseout% of Phase5%Project TeamHISD Mgr: Andreas PeeplesArchitect: Harrison KornbergContractor: Prime ContractorsProgram Mgr: Rice & GardnerGeneral OverviewNew facility for a campus accommodating 900 – 1,000 students.StatusProject closeout ongoing.NotesNoneIndicatorPlanning and Design StartEarly/Mid 2013Construction StartMid/Late 2014PhaseCloseout% of Phase50%Project TeamHISD Mgr: Andreas PeeplesArchitect: KirkseyContractor: Tellepsen BuildersProgram Mgr: Heery InternationalGeneral OverviewNew school preserving the architecturally significant building structure to accommodate 1,800 – 2,000 students.StatusProject closeout ongoing.NotesNoneIndicatorPlanning and Design StartEarly/Mid 2013Construction StartMid/Late 2014PhaseCloseout% of Phase100%Project TeamHISD Mgr: Andreas PeeplesArchitect: RdlR ArchitectsContractor: DrymallaProgram Mgr: Kwame Bldg GrpGeneral OverviewNew school for 400 students at the Houston Community College – Northline Campus.StatusCompleteNotesIndicatorPlanning and Design StartEarly/Mid 2014Construction StartMid/Late 2015PhaseConstruction% of Phase16%Project TeamHISD Mgr: Andreas PeeplesArchitect: Bay – IBIContractor: Satterfield & PontikesProgram Mgr: Heery InternationalGeneral OverviewNew facility preserving the architecturally significant building structure for a school accommodating 1,500 – 1,700 students.StatusStructural steel for culinary addition is underway. Bus loop is complete.NotesnoneIndicatorPlanning and Design StartEarly/Mid 2014Construction StartEarly/Mid 2016PhaseConstruction% of Phase50%Project TeamHISD Mgr: Andreas PeeplesArchitect: Brave ArchitectureContractor: Patriot ContractingProgram Mgr: URS-SkanskaGeneral OverviewNew school for 850 students.StatusExterior envelope, overhead MEP, and drywall framing are ongoing.NotesnoneIndicatorPlanning and Design StartLate 2015/Early 2016Construction StartMid 2016PhaseConstruction% of Phase20%Project TeamHISD Mgr: Andreas PeeplesArchitect: RDC Architects, PLLCContractor: DT ConstructionProgram Mgr: Heery International, Inc.General OverviewNew addition for a campus accommodating 750 – 900 students.StatusBuilding foundation is ongoing.NotesnoneIndicatorPlanning and Design StartEarly/Mid 2015Construction StartMid/Late 2016PhaseConstruction% of Phase20%Project TeamHISD Mgr: Dan BankheadArchitect: Stantec Architecture, Inc.Contractor: Satterfield & Pontikes Construction, Inc.Program Mgr: URS - SkanskaGeneral OverviewNew school that incorporates the new science classroom and laboratory wing for 2,550-2,750 students.StatusBuilding foundation work and tilt wall panel erection are ongoing.NotesnoneIndicatorPlanning and Design StartLate 2015/Early 2016Construction StartMid/Late 2016PhaseConstruction% of Phase57%Project TeamHISD Mgr: Andreas PeeplesArchitect: Randall - Porterfield Architects, Inc.Contractor: DT ConstructionProgram Mgr: URS - SkanskaGeneral OverviewRenovations to existing school facilities and site improvements.StatusExterior envelope and overhead MEP are ongoing for the JROTC/Performing Arts building.NotesnoneIndicatorPlanning and Design StartEarly/Mid 2013Construction StartMid/Late 2014PhaseConstruction% of Phase78%Project TeamHISD Mgr: Andreas PeeplesArchitect: Kell-Munoz Co.Contractor: ICI ConstructionProgram Mgr: URS - SkanskaGeneral OverviewNew school for 1,300-1,500 students.StatusInterior finishes are ongoing.NotesnoneIndicatorPlanning and Design StartLate 2015/Early 2016Construction StartEarly/Mid 2016PhaseCloseout% of Phase10%Project TeamHISD Mgr: Andreas PeeplesArchitect: Autoarch Architects, Inc.Contractor: DT ConstructionProgram Mgr: Rice & Gardner Consultants, Inc.General OverviewProject closeout ongoing.StatusCloseoutNotesnoneIndicatorPlanning and Design StartEarly/Mid 2013Construction StartMid/Late 2014PhaseCloseout% of Phase100%Project TeamHISD Mgr: Andreas PeeplesArchitect: Smith & Co. ArchitectsContractor: DrymallaProgram Mgr: N/AGeneral OverviewNew school for 400 students at the Houston Community College – South Campus.StatusCompleteNotesNoneIndicatorPlanning and Design StartEarly/Mid 2013Construction StartMid/Late 2014PhaseCloseout% of Phase50%Project TeamHISD Mgr: Andreas PeeplesArchitect: SHW GroupContractor: Cadence McShaneProgram Mgr: Heery InternationalGeneral OverviewNew school for 1,600 – 1,800 students.StatusProject closeout ongoing.NotesNoneIndicatorPlanning and Design StartEarly/Mid 2013Construction StartMid/Late 2014PhaseCloseout% of Phase100%Project TeamHISD Mgr: Andreas PeeplesArchitect: Natex ArchitectsContractor: DivisionOneProgram Mgr: Rice & GardnerGeneral OverviewNew addition to complete multi-phase master plan for the campus.StatusCompleteNotesNoneIndicatorPlanning and Design StartEarly/Mid 2013Construction StartMid/Late 2014PhaseCloseout% of Phase5%Project TeamHISD Mgr: Andreas PeeplesArchitect: GenslerContractor: Satterfield & PontikesProgram Mgr: Rice GardnerGeneral OverviewPartial replacement and general renovations to accommodate 1,800-2,000 students.StatusProject closeout ongoing.NotesNoneIndicatorPlanning and Design StartEarly/Mid 2013Construction StartMid/Late 2014PhaseConstruction% of Phase71%Project TeamHISD Mgr: Andreas PeeplesArchitect: Fanning-Howey/House PartnersContractor: Prime ContractorsProgram Mgr: N/AGeneral OverviewNew school for 1,100-1,300 students.StatusExterior envelope, overhead MEP, and drywall framing are ongoing.NotesnoneIndicatorPlanning and Design StartLate 2015/Early 2016Construction StartLate 2016PhaseConstruction% of Phase68%Project TeamHISD Mgr: Andreas PeeplesArchitect: Joiner Partnership, Inc.Contractor: Satterfield & Pontikes Construction, Inc.Program Mgr: Rice & Gardner Consultants, Inc.General OverviewPartial replacement and general renovations to accommodate 2,300-2,500 students.StatusExterior envelope, overhead MEP, and drywall framing are ongoing.NotesnoneIndicatorPlanning and Design StartLate 2015/Early 2016Construction StartLate 2016PhaseConstruction% of Phase23%Project TeamHISD Mgr: Dan BankheadArchitect: H. Munoz & Company, Inc.Contractor: DivisionOne ConstructionProgram Mgr: Heery International, Inc.General OverviewNew addition and general renovations of the existing facilities to accommodate 750-900 students.StatusBuilding foundation is ongoing.NotesnoneIndicatorPlanning and Design StartLate 2015/Early 2016Construction StartLate 2016PhaseConstruction% of Phase43%Project TeamHISD Mgr: Andreas PeeplesArchitect: Smith & Company Architects, Inc.Contractor: Drymalla Construction Co.Program Mgr: Rice & Gardner Consultants, Inc.General OverviewNew addition and general renovations to accommodate 750-900 students.StatusMasonry, overhead MEP, and drywall installation are ongoing.NotesnoneIndicatorPlanning and Design StartEarly/Mid 2013Construction StartMid/Late 2014PhaseCloseout% of Phase5%Project TeamHISD Mgr: Andreas PeeplesArchitect: WHR & Lake|FlatoContractor: Satterfield & PontikesProgram Mgr: URS - SkanskaGeneral OverviewNew school for 1,700-1,900 students.StatusProject closeout ongoing.NotesNoneIndicatorPlanning and Design StartEarly/Mid 2013Construction StartMid/Late 2014PhaseConstruction% of Phase20%Project TeamHISD Mgr: Andreas PeeplesArchitect: Molina WalkerContractor: B3CiProgram Mgr: N/AGeneral OverviewNew facility that will incorporate the new two-story classroom wing for a campus accommodating 1,100 – 1,300 students.StatusFoundation work is ongoing.NotesNoneIndicatorPlanning and Design StartEarly/Mid 2014Construction StartMid/Late 2015PhaseConstruction% of Phase50%Project TeamHISD Mgr: Andreas PeeplesArchitect: Moody NolanContractor: Turner ConstructionProgram Mgr: N/AGeneral OverviewNew school for 1,300-1,500 students.StatusExterior envelope, overhead MEP, and drywall framing are ongoing.NotesnoneIndicatorPlanning and Design StartEarly/Mid 2015Construction StartMid/Late 2016PhaseConstruction% of Phase60%Project TeamHISD Mgr: Andreas PeeplesArchitect: Natex CorporationContractor: Satterfield & Pontikes Construction, Inc.Program Mgr: Heery International, Inc.General OverviewPartial replacement and general renovations for a campus accommodating 900-1,000 students.StatusBuilding addition is complete and in use. Renovation work is ongoing.Notesnone