7/7/21 Project Update
Please click on the link below to see the current proposed timeline for Sinclair's Expansion Project.
-
4/28/21 Project Update
Please click on the link below to see the current proposed timeline for Sinclair's Expansion Project.
-
4/27/21 Project update
On Wednesday, April 28th. 2021, a fencing company will be on-site. Construction will then begin on Thursday, April 29th, 2021.
-
4/7/21 Project Update
On this weekend, both Saturday April 10th, and Sunday April 11th, one shed is scheduled to be demolished and the other one is scheduled to be moved. The trees in this area are also scheduled to be removed.
-
3/8/21 Project Update
A crew of contractors will be coming to the campus on Saturday 13th and Sunday 14th of March to begin cutting trees.