Grady Middle School

  • pic1

Description

  • This is an expansion project with two project phases.The first phase will demolish original building, recreation building, and basketball courts.It will include construction of a gym and 2-story administration building. The second phase will remove T-buildings and construct a 2-story academic wing.

Project Status

  • Project is complete and in the 1-year warranty period.Submission of final documentation is underway and close out procedures are in progress.

Information

  • Grady Middle School
    5215 San Felipe
    Houston, Texas 77056
    Phone: 713-625-1411
    Fax: 713-625-1415

Facts

    • Project C-068
    • Budget: $13,658,245
    • Project Type: Expansions
    • Current Phase: Warranty Phase
    • Progress: 90%

Project Information

    • Feeder: Lee High School
    • District: District VII - Harvin C. Moore
    • CMPA: Rice & Gardner
    • Manager: Bruce Green
    • Contractor: Satterfield & Pontikes
    • Architect: Gensler Architects